Summer Limited Time 60% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: dealsixty

CIPS Level 4 Diploma in Procurement and Supply L4M3 Full Course Free

Page: 6 / 6
Question 24

Which of the following is the best definition of “ultra vires”?

Options:

A.

Beyond powers

B.

In good faith

C.

From one party

D.

Let the buyer beware

Question 25

XYZ Ltd is negotiating a long-term supply contract of important parts with a supplier. Dave, procurement manager teams up with Alla, legal manager to construct a service level agreement. Dave is concerned that poor performance of supplier may cause damages to the operations of the organisation. Which of the following can be used in conjunction with SLA to compensate the buying organisation in case of supplier's poor performance?

1. Warranties

2. Force majeure clauses

3. Penalty clauses

4. Service credits

Options:

A.

1 and 3 only

B.

3 and 4 only

C.

1 and 2 only

D.

4 and 2 only

Question 26

Which of the following would be useful tools to incentivise supplier innovation over the duration of the contract?

1. Gainshare arrangement

2. Liquidated damages

3. Service credits

4. Fixed bonus payments

Options:

A.

3 and 4 only

B.

2 and 4 only

C.

1 and 4 only

D.

1 and 3 only

Question 27

GPP, the employer, and Prosolia UK, the contractor, entered into five EPC contracts for the development of five different solar power generation plants in the United Kingdom. Four out of the five developments failed to be commissioned by the relevant due dates, with the delays ranging from 44 to 285 days.

Among other claims, GPP, acting through its two investment vehicles, claimed liquidated damages of £500 per day in all four contracts for Prosolia UK's failure to achieve completion of the plants by the due date. The liquidated damages claimed amounted to £1,804,221 across the four delayed contracts.

Prosolia, alongside various other defences, raised the defence that the liquidated damages provision in each contract was a penalty, and therefore unenforceable against it. Is Prosolia contractually obliged to make the payment to the plaintiff?

Options:

A.

No, the amount claimed is too excessive and it may put Prosolia into insolvency. The clause must be void

B.

No, the clause must be treated as a penalty clause which is unenforceable in UK

C.

Yes, the amount is a reward to the employer as they have supervised and monitored the projects

D.

Yes, the clause is a genuine estimate of possible losses that GPP may have suffered and therefore, it is enforceable.

Page: 6 / 6
Exam Code: L4M3
Exam Name: Commercial Contracting
Last Update: Apr 18, 2024
Questions: 190
L4M3 pdf

L4M3 PDF

$32  $80
L4M3 Engine

L4M3 Testing Engine

$38  $95
L4M3 PDF + Engine

L4M3 PDF + Testing Engine

$52  $130