Scrum SMC Questions Answers

Page: 5 / 5
Question 20

Which of the following is/are role(s) of a Chief Scrum Master, not of a Chief Product Owner?

A) Addresses impediments that impact more than one Scrum Team.

B) Prepares and maintains the overall Prioritized Product Backlog for the large project.

C) Facilitates the Scrum of Scrums meetings.

D) Interfaces with the Program Product Owner to ensure alignment of the large project with the goals and

objectives of the Program.

Options:

A.

A and C

B.

A and D

C.

A, B, and C

D.

C

Question 21

You are the Scrum Master for the ID7 Project for your organization. Martha is serving as the Product Owner for this project. Martha meets with you and asks for your advice on how she should go about estimating the work in the Product Backlog. What should you tell Martha?

Options:

A.

The Development Team will work with Martha to estimate the items in the Product Backlog with story points.

B.

The Development Team will work with you, the Scrum Master, to create time and cost estimates for all the Product Backlog items.

C.

Martha can estimate the items in the Product Backlog, but you, the Scrum Master, must be approve the estimates prior to each Sprint Planning meeting.

D.

Martha can estimate the items in the Product Backlog, but the Development Team must approve the estimates prior to the Sprint beginning.

Question 22

Which of the following comparisons is true about Scrum and Traditional Project Management?

Options:

A.

In Scrum, upfront planning is high, while in Traditional Project Management it is low.

B.

In Scrum, performance measurement is based on plan conformity, while in Traditional Project

Management it is based on business value.

C.

In Scrum, customer involvement is high throughput the project, while in Traditional Project it varies

according to the project's lifecycle.

D.

In Scrum, Quality Assurance is process centric, while in Traditional Project Management it is customer

centric.

Page: 5 / 5
Exam Code: SMC
Exam Name: Scrum Master Certified (SMC)
Last Update: Apr 24, 2024
Questions: 147
SMC pdf

SMC PDF

$28  $80
SMC Engine

SMC Testing Engine

$33.25  $95
SMC PDF + Engine

SMC PDF + Testing Engine

$45.5  $130