Question # 54

During which process does the project team receive bids and proposals?

Options:

A.

Conduct Procurements

B.

Plan Procurements

C.

Estimate Costs

D.

Control Budget

Buy Now
Question # 55

An element of the modern quality management approach used to achieve compatibility with the International Organization for Standardization (ISO) is known as:

Options:

A.

Forecasting,

B.

Brainstorming.

C.

Historical databases.

D.

Cost of quality.

Buy Now
Question # 56

Project managers who lead by example and follow through on the commitments they make demonstrate the key interpersonal skill of:

Options:

A.

influencing

B.

leadership

C.

motivation

D.

coaching

Buy Now
Question # 57

The following is a network diagram for a project.

The free float for Activity H is how many days?

Options:

A.

4

B.

5

C.

10

D.

11

Buy Now
Question # 58

The most appropriate project life cycle model for an environment with a high level of change and extensive stakeholder involvement in projects is:

Options:

A.

adaptive

B.

reflexive

C.

predictive

D.

iterative

Buy Now
Question # 59

Which of the Perform Quality Assurance tools and techniques may enhance the creation of the work breakdown structure (VVBS) to give structure to the decomposition of the scope?

Options:

A.

Activity network diagrams

B.

Affinity diagrams

C.

Matrix diagrams

D.

Interrelationship digraphs

Buy Now
Question # 60

Funding limit reconciliation is a tool and technique of which Project Cost Management process?

Options:

A.

Estimate Costs

B.

Control Costs

C.

Plan Cost Management

D.

Determine Budget

Buy Now
Question # 61

The process of monitoring the status of the project and product scope as well as managing the changes to the scope baseline is known as:

Options:

A.

Validate Scope.

B.

Plan Scope Management.

C.

Control Scope.

D.

Define Scope.

Buy Now
Question # 62

The following is a network diagram for a project.

The free float for Activity E is how many days?

Options:

A.

2

B.

3

C.

5

D.

8

Buy Now
Question # 63

The lowest level normally depicted in a work breakdown structure (VVBS) is called a/an:

Options:

A.

work package

B.

deliverable

C.

milestone

D.

activity

Buy Now
Exam Code: PMI-100
Exam Name: Certified Associate in Project Management (CAPM)®
Last Update: Aug 22, 2025
Questions: 704
PMI-100 pdf

PMI-100 PDF

$25.5  $84.99
PMI-100 Engine

PMI-100 Testing Engine

$28.5  $94.99
PMI-100 PDF + Engine

PMI-100 PDF + Testing Engine

$40.5  $134.99