Question # 84

The process of identifying specific actions to be performed to produce project deliverables is:

Options:

A.

Define Activities.

B.

Create WBS.

C.

Define Scope.

D.

Develop Schedule.

Buy Now
Question # 85

The staffing management plan is part of the:

Options:

A.

organizational process assets.

B.

resource calendar.

C.

human resource plan.

D.

Develop Project Team process.

Buy Now
Question # 86

While preparing the project management plan on a weekly basis, the project manager indicates the intention to provide an issues report to the staff via e-mail. In which part of the plan will this type of information be included?

Options:

A.

Communications management plan

B.

Human resource plan

C.

Quality management plan

D.

Procurement management plan

Buy Now
Question # 87

Which tools or techniques will a project manager use for Develop Project Team?

Options:

A.

Negotiation

B.

Roles and responsibilities

C.

Recognition and rewards

D.

Prizing and promoting

Buy Now
Question # 88

What is the total float of the critical path?

Options:

A.

Can be any number

B.

Zero or positive

C.

Zero or negative

D.

Depends on the calendar

Buy Now
Question # 89

Which Knowledge Area is concerned with the processes required to ensure timely and appropriate generation, collection, distribution, storage, retrieval, and ultimate disposition of project information?

Options:

A.

Project Integration Management

B.

Project Communications Management

C.

Project Information Management System (PIMS)

D.

Project Scope Management

Buy Now
Question # 90

Which process involves aggregating the estimated costs of the individual schedule activities or work packages?

Options:

A.

Estimate Costs

B.

Estimate Activity Resources

C.

Control Costs

D.

Determine Budget

Buy Now
Question # 91

Information collected on the status of project activities being performed to accomplish the project work is known as what?

Options:

A.

Project management information system

B.

Work performance information

C.

Work breakdown structure

D.

Variance analysis

Buy Now
Question # 92

An output of Control Schedule is:

Options:

A.

A project schedule network diagram

B.

A schedule management plan

C.

Schedule data

D.

Schedule forecasts

Buy Now
Question # 93

Who selects the appropriate processes for a project?

Options:

A.

Project stakeholders

B.

Project sponsor and project stakeholder

C.

Project manager and project team

D.

Project manager and project sponsor

Buy Now
Exam Code: PMI-100
Exam Name: Certified Associate in Project Management (CAPM)®
Last Update: Aug 22, 2025
Questions: 704
PMI-100 pdf

PMI-100 PDF

$25.5  $84.99
PMI-100 Engine

PMI-100 Testing Engine

$28.5  $94.99
PMI-100 PDF + Engine

PMI-100 PDF + Testing Engine

$40.5  $134.99