Pre-Summer Sale 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: Board70

AgilePM-Practitioner Exam Dumps - APMG-International AgilePM Questions and Answers

Question # 34

Using the Project Scenario, answer the following question about the activities in the Agile project lifecycle.

Lines 1 to 5 in the table below consist of an assertion statement and a reason statement. For each line identify the appropriate option, from options A to E, that applies. Each option can be used once, more than once or not at all.

Assertion:-

1. The rooms and facilities must be deployed into live use at the end of each Timebox.

BECAUSE

Reason:

Evolutionary Development and Deployment must be combined in a Timebox where the integration of several teams is required.

2. The tasks associated with each Solution Development Timebox should be included

in the Delivery Plan.

BECAUSE

Reason:

A typical Delivery Plan will provide a schedule of Timeboxes and any other high level activities for the imminent Project Increment.

3. The development approach should have been agreed during Foundations.

BECAUSE

Reason:

The Development Approach Definition must be created before Evolutionary

Development can commence.

4. The resources from Timber Tigers and Earth Excavations should have been engaged

before the start of Evolutionary Development.

BECAUSE

Reason:

Commitment to delivery is based on pre-agreed resource levels at the project level.

5. A final Deployment phase should be held after Timebox C has completed.

BECAUSE

Reason:

The Deployed Solution is assessed post-project to confirm whether the expected benefits have been

achieved.

Options:

Buy Now
Question # 35

Using the project timeline given in the Project Scenario, answer the following question about application of Timeboxing on the Hoy Hall project.

Lines 1 to 5 in the table below consist of an assertion statement and a reason statement. For each line identify the appropriate option, from options A to E, that applies.

Each option can be used once, more than once or not at all.

Assertion :

1. All internal works to be assigned to Timber Tigers throughout the project should be consolidated into one Structured Timebox.

BECAUSE

The Investigation step within each Structured Timebox requires everyone working within the team to jointly agree how the requirements of the Timebox will be met.

2. Acceptance criteria for the front rooms to be developed in Timebox A should be described in detail and agreed during the Timebox Kick-Off

BECAUSE

The aim of the Investigation step within each Timebox is to complete as much of

the development work as possible.

3. It is appropriate that both the Evolutionary Development phase and Deployment phase are shown in the first Project Increment.

BECAUSE

Each Timebox should comprise an Evolutionary Development phase and

Deployment phase.

4. It is appropriate that the outputs of Timebox C are scheduled for deployment at the end of the first Project Increment.

BECAUSE

A typical Timebox Plan should provide a schedule of high-level activities for the

imminent Project Increment.

5. It is appropriate that Earth Excavations create a detailed plan of activities they will complete during Timebox C.

Reason

BECAUSE

The Solution Development Team is responsible for planning the detail of all the

work of each Timebox.

Options:

Buy Now
Question # 36

Using the Project Scenario and the additional information provided for this question in the Scenario Booklet, answer the following questions about applying

controls to the end of Development Timebox C.

What action should the Project Manager take when considering the End of Timebox Review?

Options:

A.

Encourage the Marketing Director to attend the End of Timebox Review.

B.

Attend the next Daily Stand-up to raise an issue about the windows.

C.

Prepare a summary of progress against plan, for presentation at the review.

D.

Ask the Team Leader to remove the windows from the Timebox Plan for Timebox C.

Buy Now
Question # 37

How should the lack of provision of a fire escape from the upstairs of the building in Timebox B initially be dealt with?

Options:

A.

The Solution Development Team should revise the Timebox Plans for Timeboxes B and C.

B.

The Solution Development Team should commence understanding and delivering the new requirement.

C.

The Architect, in the role of Technical Co-ordinator, should escalate the issue to Architecture Angels ' Senior Management Team.

D.

The Project Manager should escalate the issue to the Marketing Director, who is in the role of Business Visionary.

Buy Now
Question # 38

Several of the web developers working on the project have no Agile

experience. When answering the questions in the Project Approach

Questionnaire (PAQ), the Project Manager could not agree with the statement

' all members of the project understand and accept the DSDM approach ' .

What action should the Project Manager take?

Options:

A.

Replace the web developers with experienced Agile practitioners.

B.

Agree with the statement in the PAQ and keep a close watch on the web

developers throughout the project.

C.

Organize a training workshop to brief all project-level and Solution

Development Team roles in the Agile approach.

D.

Accept that the web developers are experts in their field and will be

adopting their own approach throughout the project.

Buy Now
Question # 39

Towards the end of the Foundations phase of Project Increment 4, with the high-level requirements agreed, Hira, has asked the Developers to estimate the work required to deliver the Eco spa solution.

(The Developers have used the Planning Poker technique to generate their estimates. Hira now needs to determine how many Sprints will be required for the Delivery Teams to deliver the Eco-spa.

What should the Developers do to help Hira make this decision?)

Options:

A.

They should use the commitment-based planning technique to estimate how many story points of work can be achieved in a Sprint.

B.

They should convert story points to person days, allowing Hira to establish how many Sprints will be needed based on development capacity.

C.

They should assign average time allocations for each backlog item, making it easy for Hira to ensure that every Sprint has an equal workload.

D.

They should re-estimate using a more appropriate technique because Story Point estimating intentionally avoids associating time with effort.

Buy Now
Question # 40

Mira Bachar has spoken with a guest who wanted an aromatherapy scent to remember their holiday. Inspired by this, Mira suggested creating a unique aromatherapy oil for spa treatments and guest sales, which could also serve as a marketing tool.

Brinda Vyas supports exploring the idea, but Sukra Aroon notes that selling products is not in scope and could introduce complexities.

(Hira is holding a series of 2-hour estimation workshops for Project Increment 4.

Which 2 of the following instructions provide appropriate guidance to the workshop attendees?)

Options:

A.

Develop task-level estimates for all work within the Project Increment.

B.

Use Planning Poker to generate precise estimates for infrastructure, treatments, and IT.

C.

Allow flexibility and accept uncertainty in estimates that may be refined later.

D.

Ensure estimates are fixed and precise to maintain accountability.

E.

Use team-based estimation techniques as collective knowledge will improve accuracy.

Buy Now
Question # 41

(New food hygiene laws take effect in six months. Sukra Aroon and Wanida Anong are assessing if kitchen remodeling is needed, which may divert Infrastructure Team resources.)

Options:

A.

Approach-based, because past Project Increment planning failed to account for regulatory change, causing lack of contingency and resource risks.

B.

Approach-based, because Sukra Aroon should have tracked evolving legislation from the start to mitigate the risk.

C.

VUCA-based, because new legislation is an external factor requiring adaptability to respond to unplanned demands.

D.

VUCA-based, because gaps in internal compliance cause uncertainty in responding to changing regulations.

Buy Now
Question # 42

(Which 2 statements describe appropriate team behaviour for effective risk management?)

Options:

A.

Team members should adopt a collaborative mindset, sharing responsibility for identifying and mitigating risks.

B.

Hira should have sole responsibility for managing all risks with clear accountability.

C.

Developers should resolve all risks collaboratively and promptly without escalation.

D.

Sukra Aroon should handle all technical risks independently to ensure the solution is fit for purpose.

E.

Risk management should be proactive and part of daily activities, not a separate process.

Buy Now
Question # 43

Mira Bachar has spoken with a guest who wanted an aromatherapy scent to remember their holiday. Inspired by this, Mira suggested creating a unique aromatherapy oil for spa treatments and guest sales, which could also serve as a marketing tool.

Brinda Vyas supports exploring the idea, but Sukra Aroon notes that selling products is not in scope and could introduce complexities.

(When defining and estimating work for Project Increment 4, the Delivery Teams must account for uncertainty in integrating the Eco-spa into the guest experience.

Which 2 of the following approaches align with AgilePM principles for managing uncertainty in estimation?)

Options:

A.

Use broad estimation ranges for high-uncertainty work and refine estimates as more information becomes available.

B.

Avoid committing to estimates for uncertain work until all unknowns are resolved.

C.

Identify key assumptions behind estimates and revisit them regularly as the project evolves.

D.

Ensure all estimates are fixed early to maintain control over scope and budget.

E.

Exclude uncertain work from estimation until development is underway and clearer details emerge.

Buy Now
Exam Name: Agile Project Management (AgilePM) Practitioner Exam
Last Update: May 21, 2026
Questions: 184
AgilePM-Practitioner pdf

AgilePM-Practitioner PDF

$25.5  $84.99
AgilePM-Practitioner Engine

AgilePM-Practitioner Testing Engine

$28.5  $94.99
AgilePM-Practitioner PDF + Engine

AgilePM-Practitioner PDF + Testing Engine

$40.5  $134.99