Using the Project Scenario, answer the following question about the activities in the Agile project lifecycle.
Lines 1 to 5 in the table below consist of an assertion statement and a reason statement. For each line identify the appropriate option, from options A to E, that applies. Each option can be used once, more than once or not at all.

Assertion:-
1. The rooms and facilities must be deployed into live use at the end of each Timebox.
BECAUSE
Reason:
Evolutionary Development and Deployment must be combined in a Timebox where the integration of several teams is required.
2. The tasks associated with each Solution Development Timebox should be included
in the Delivery Plan.
BECAUSE
Reason:
A typical Delivery Plan will provide a schedule of Timeboxes and any other high level activities for the imminent Project Increment.
3. The development approach should have been agreed during Foundations.
BECAUSE
Reason:
The Development Approach Definition must be created before Evolutionary
Development can commence.
4. The resources from Timber Tigers and Earth Excavations should have been engaged
before the start of Evolutionary Development.
BECAUSE
Reason:
Commitment to delivery is based on pre-agreed resource levels at the project level.
5. A final Deployment phase should be held after Timebox C has completed.
BECAUSE
Reason:
The Deployed Solution is assessed post-project to confirm whether the expected benefits have been
achieved.


Using the project timeline given in the Project Scenario, answer the following question about application of Timeboxing on the Hoy Hall project.
Lines 1 to 5 in the table below consist of an assertion statement and a reason statement. For each line identify the appropriate option, from options A to E, that applies.
Each option can be used once, more than once or not at all.

Assertion :
1. All internal works to be assigned to Timber Tigers throughout the project should be consolidated into one Structured Timebox.
BECAUSE
The Investigation step within each Structured Timebox requires everyone working within the team to jointly agree how the requirements of the Timebox will be met.
2. Acceptance criteria for the front rooms to be developed in Timebox A should be described in detail and agreed during the Timebox Kick-Off
BECAUSE
The aim of the Investigation step within each Timebox is to complete as much of
the development work as possible.
3. It is appropriate that both the Evolutionary Development phase and Deployment phase are shown in the first Project Increment.
BECAUSE
Each Timebox should comprise an Evolutionary Development phase and
Deployment phase.
4. It is appropriate that the outputs of Timebox C are scheduled for deployment at the end of the first Project Increment.
BECAUSE
A typical Timebox Plan should provide a schedule of high-level activities for the
imminent Project Increment.
5. It is appropriate that Earth Excavations create a detailed plan of activities they will complete during Timebox C.
Reason
BECAUSE
The Solution Development Team is responsible for planning the detail of all the
work of each Timebox.


Using the Project Scenario and the additional information provided for this question in the Scenario Booklet, answer the following questions about applying
controls to the end of Development Timebox C.
What action should the Project Manager take when considering the End of Timebox Review?
How should the lack of provision of a fire escape from the upstairs of the building in Timebox B initially be dealt with?
Several of the web developers working on the project have no Agile
experience. When answering the questions in the Project Approach
Questionnaire (PAQ), the Project Manager could not agree with the statement
' all members of the project understand and accept the DSDM approach ' .
What action should the Project Manager take?
Towards the end of the Foundations phase of Project Increment 4, with the high-level requirements agreed, Hira, has asked the Developers to estimate the work required to deliver the Eco spa solution.

(The Developers have used the Planning Poker technique to generate their estimates. Hira now needs to determine how many Sprints will be required for the Delivery Teams to deliver the Eco-spa.
What should the Developers do to help Hira make this decision?)
Mira Bachar has spoken with a guest who wanted an aromatherapy scent to remember their holiday. Inspired by this, Mira suggested creating a unique aromatherapy oil for spa treatments and guest sales, which could also serve as a marketing tool.
Brinda Vyas supports exploring the idea, but Sukra Aroon notes that selling products is not in scope and could introduce complexities.

(Hira is holding a series of 2-hour estimation workshops for Project Increment 4.
Which 2 of the following instructions provide appropriate guidance to the workshop attendees?)
(New food hygiene laws take effect in six months. Sukra Aroon and Wanida Anong are assessing if kitchen remodeling is needed, which may divert Infrastructure Team resources.)
(Which 2 statements describe appropriate team behaviour for effective risk management?)
Mira Bachar has spoken with a guest who wanted an aromatherapy scent to remember their holiday. Inspired by this, Mira suggested creating a unique aromatherapy oil for spa treatments and guest sales, which could also serve as a marketing tool.
Brinda Vyas supports exploring the idea, but Sukra Aroon notes that selling products is not in scope and could introduce complexities.

(When defining and estimating work for Project Increment 4, the Delivery Teams must account for uncertainty in integrating the Eco-spa into the guest experience.
Which 2 of the following approaches align with AgilePM principles for managing uncertainty in estimation?)