CDCS Exam Dumps - Exin EPI Data Centre Questions and Answers

Question # 24

You are installing new copper cabling.

What is the advantage or disadvantage of choosing pre-terminated category 6 or 6A cabling?

Options:

A.

Pre-terminated cabling is already factory tested and saves installation time.

B.

There is no advantage as most new copper cabling network designs are based on category 3 or 5E for horizontal cabling.

C.

Pre-terminated cabling has a higher fire rating.

D.

Pre-terminated cabling makes ordering of the copper cables more complex, as you need to know in advance on which side the male or female connector needs to be located.

Buy Now
Question # 25

What is the main disadvantage of using a ToR (Top of Rack) design?

Options:

A.

A single ToR (Top of Rack) switch is more expensive than an EoR (End of Row) switch.

B.

You need a separate rack to install all your ToR (Top of Rack) switches.

C.

There will be more switches to manage.

D.

A ToR (Top of Rack) switch has only optical interfaces.

Buy Now
Question # 26

The humidity in the computer room has increased from about 60% up to 85% Relative Humidity (RH). What potential risk does this pose to your equipment?

Options:

A.

No risks at all

B.

The risk of excessive wear and corrosion will increase

C.

The electrostatic discharge (ESD) levels will go up

D.

There will be a cooling risk due to a high wet bulb temperature

Buy Now
Question # 27

The location of a data center is just above the Arctic Circle (North Pole). The outside air temperature is never above 21°C/70°F.

Taking energy efficiency as the highest priority, which cooling system should you recommend?

Options:

A.

Standard air conditioning units, as spares might not be readily available

B.

Any cooling system can be efficient because the outside air temperature will not influence the temperature of the air intake of the ICT equipment

C.

Waterside economizer

D.

Airside economizer

Buy Now
Question # 28

The electrical diagram of the data center shows the following UPS configuration and has a load of 80 kW.

What is the set-up in this data center?

Options:

A.

2+N+1

B.

2(N+1)

C.

N+N(+1)

D.

(N+1)-(N+1)

Buy Now
Question # 29

What is the first step in the design stage of the data center life cycle?

Options:

A.

Select vendors

B.

Do a design validation

C.

Define the scope of the project

D.

Freeze the design

Buy Now
Question # 30

A data center requires an audit to find out whether it conforms with ANSI/TIA-942 Rated-3 (concurrently maintainable).

Will the network architecture be part of this audit?

Options:

A.

No, as concurrently maintainable only applies to electrical and mechanical (power and cooling).

B.

Yes, but only if the network administration does not comply with ANSI/TIA-606.

C.

Yes, amongst other aspects, the network architecture should be Rated-3 compliant with the requirements of ANSI/TIA-942.

D.

No, only the type of cabling used will be audited.

Buy Now
Question # 31

Where should raised-floor installation start?

Options:

A.

Point A (entrance corner)

B.

Point B (side wall)

C.

Point C (center of the room)

D.

Point D (corner opposite entrance)

Buy Now
Question # 32

You want to manage temperature and humidity only at the facility level in your data center. All servers use front-to-rear airflow. Which location for measurement should you recommend?

Options:

A.

At the back/rear of the server at 50 mm (2 in)

B.

At 1.5 m (5 ft) above the floor, 0.4 m (15 in) in front of the rack

C.

At the front/intake of the server at 50 mm (2 in)

D.

At 1.5 m (5 ft) above the floor, 0.4 m (15 in) at the back of the rack

Buy Now
Question # 33

What is the advantage or disadvantage of using MPO (Multi-fiber Push On)/pre-terminated fiber?

Options:

A.

There is no advantage, as it cannot be used with OM4 optical fiber cables.

B.

There is no advantage, as it creates additional heat load in the data center.

C.

It speeds up installation and provides an easy upgrade to transmission speeds up to 40 Gbit/s -100 Gbit/s.

D.

It is a very flexible system as it can be used for both copper cables and optical fiber cables.

Buy Now
Exam Code: CDCS
Exam Name: EXIN EPI Certified Data Centre Specialist
Last Update: Oct 18, 2025
Questions: 120
CDCS pdf

CDCS PDF

$25.5  $84.99
CDCS Engine

CDCS Testing Engine

$28.5  $94.99
CDCS PDF + Engine

CDCS PDF + Testing Engine

$40.5  $134.99