Your company is about to start a project to replace an old sales and merchandising system with a new version that will be based on modern platforms. The main requirements for the system are:
1. Loading sales data, sent electronically from the stores each evening, into a central database.
2. Producing sales reports for the merchandisers, whose job is to manage stock levels in stores.
3. Producing forecast reports, used to predict future demand for each product, based on a combination of sales history and forecasting parameters. The parameters will be entered by the merchandisers into a browser-based front end and the reports will be produced overnight. The users will be able to retrieve the reports, on screen or in print, via an interactive feature.
Requirements 1 and 2 were already met by the old system and will be rewritten in the new system with some minor functional changes. The sales data will, as before, be loaded in an overnight batch run. There have been problems with the old system at peak periods when this run has taken longer than scheduled, so that dependent jobs could not finish before the start of the next working day. The Data Centre manager requires that the new system's overnight batch runs take 10% less time than the old one, including the new reports, to allow time for all jobs to complete.
Requirement 3 is new. The functionality provided by the UI will be simple and the Sales & Merchandising manager requires that it be easy to use.
The data for testing the reports will be extracted from the old system in production and will be anonymized before use.
The system will be developed using an Agile lifecycle with iterations of fixed length. This will be the first full deployment of this methodology, which has just completed a successful pilot. It is a relatively simple development and is expected to be completed in three releases, each taking approximately two months.
Until now the company has not automated test execution, but the Agile pilot identified this as a critical success factor. You are an experienced TAE and have been recruited to implement test automation, and you are now considering what the TAS for this should look like.
Which option contains the THREE MOST important considerations in determining the nature of the TAS that will be needed for this project?
i) The tool(s) chosen for functional test automation should support scripting techniques that will be compatible with a performance test tool.
ii) The tool(s) chosen for functional test automation should support scripting techniques that will be useful for usability testing.
iii) The TAS should support testing at the component integration, system, system integration and acceptance levels.
iv) The TAS should support testing at the component, component integration, system and acceptance levels.
v) The TAS should support the handling of the large quantities of data that will be needed to test the forecast reports.
Which of the following layers within the TAA contains technology-specific implementations that enable automated tests to have the execution of their logical actions result in actual interaction with the appropriate interfaces of the SUT?
You are evaluating the best approach to implement automated tests at the UI level for a web app. Specifically, your goal is to allow test analysts to write automated tests in tabular format, within files that encapsulate logical test steps related to how a user interacts with the web UI, along with the corresponding test data. These steps must be expressed using natural language words that represent the actions performed by the user on the web UI. These files will then be interpreted and executed by a test execution tool. Which of the following approaches to test automation is BEST suited to achieve your goal?
Which ONE of the four layers of the test automation architecture provides an optional capability?
Your TAF writes detailed test logs for every test that it executes. Data storage space in the test environment is limited, so after each run it is necessary to remove unnecessary detail from the log for tests that passed and move the data that must be kept to a different place.
What would be the BEST way to do this?
Which of the following descriptions of what some test automation tools can be used to do is TRUE?