Question # 14

During routine maintenance of the lithium battery cabinet, which of the following procedure is true about replacing a faulty battery module?

Options:

A.

1-6-3-2-5-7-4

B.

1-3-2-6-5-7-4

C.

1-6-2-5-3-7-4

D.

1-2-3-6-5-7-4

Buy Now
Question # 15

Which of the following is not a scenario-based solution for Huawei data center products?

Options:

A.

FusionDC800

B.

FusionDC1000

C.

FusionModule500

D.

FusionModule2000

Buy Now
Question # 16

In a data center fire protection design, which approach best matches Huawei facility practice for protecting IT rooms while minimizing secondary damage to IT equipment?

Options:

A.

Use only portable extinguishers and rely on manual response

B.

Deploy a smoke detection system plus a clean-agent gas extinguishing system with interlock controls for automatic release

C.

Install a water sprinkler system as the only suppression method inside the IT white space

D.

Disable automatic suppression to avoid accidental discharge

Buy Now
Question # 17

Which of the following statements are true about the industry trend of the data center cooling systems?

Options:

A.

Liquid cooling systems are widely used in high-density solutions.

B.

Cloud + AI – data centers enter a new energy-saving era.

C.

Evaporative cooling systems become the main solution for large data centers.

D.

Higher inlet and outlet water temperatures are the trend of large data center cooling.

Buy Now
Question # 18

When a critical alarm is generated in a lithium battery cabinet and the buzzer beeps continuously, the status of the indicator on the MDU is

Options:

A.

Blinking yellow fast

B.

Steady yellow

C.

Blinking red fast

D.

Steady red

Buy Now
Question # 19

Which of the following is the procedure for replacing a damaged UPS power module onsite?

Options:

A.

①③

B.

①④

C.

②③

D.

②④

Buy Now
Question # 20

In a data center power distribution architecture, what is the primary function of a Static Transfer Switch (STS) for critical single-cord loads?

Options:

A.

Convert AC power to DC power for IT equipment

B.

Provide fast switching between two independent AC power sources to maintain continuity

C.

Reduce harmonic distortion by filtering non-linear loads

D.

Increase the output frequency from 50 Hz to 60 Hz

Buy Now
Question # 21

After installing the FusionCol8000-C (110–440 kW), inject water to preserve the pressure for the chilled water pipes to how many MPa. After 30 minutes, check that no leakage occurs. Preserve the pressure for 24 hours. If the pressure drop is less than 0.01 MPa and no leakage occurs, the pipes do not leak.

Options:

A.

0.8

B.

0.5

C.

1

D.

1.2

Buy Now
Exam Code: H20-923_V1.0
Exam Name: HCSP-Field-Data Center Facility V1.0
Last Update: Feb 20, 2026
Questions: 60
H20-923_V1.0 pdf

H20-923_V1.0 PDF

$25.5  $84.99
H20-923_V1.0 Engine

H20-923_V1.0 Testing Engine

$28.5  $94.99
H20-923_V1.0 PDF + Engine

H20-923_V1.0 PDF + Testing Engine

$40.5  $134.99