Question # 4

Currently, your Development Teams are organized to address a single layer only (for example, front end, middle tier, back end, and interfaces). What are three things to consider when deciding to move away from such component teams toward feature teams? (Choose three.)

Options:

A.

You cannot do Scrum without feature teams.

B.

Productivity may suffer when making this kind of move.

C.

Getting support from the business side first helps.

D.

Feature teams have less communication overhead.

E.

With feature teams, it is easier to calculate the productivity per team.

Buy Now
Question # 5

Which statement best describes Scrum?

Options:

A.

A defined and predictive process that confirms to the principles of Scientific Management.

B.

A complete methodology that defines how to develop software.

C.

A cookbook that defines best practices for software development.

D.

A framework within which complex products in complex environments are developed.

Buy Now
Question # 6

Which of the following is an example of an Increment? (Choose the best answer.)

Options:

A.

A plan for the overall product release.

B.

A mock-up of the product marketing materials.

C.

A design for the product.

D.

A product roll-out plan.

E.

A valuable, useful set of products featured.

F.

All of the above.

Buy Now
Question # 7

In the Sprint Planning meeting, the Product Owner and the Development Team were unable to reach a clear understanding about the highest order Product Backlog items. Because of this, the Development Team couldn’t figure out how many Product Backlog items it could forecast for the upcoming Sprint. They were able to agree on a Sprint Goal, however.

Which of the following two actions should the Scrum Master support? (Choose two.)

Options:

A.

Cancel the Sprint. Send the entire team to an advanced Scrum training and then start a new Sprint.

B.

Forecast the most likely Product Backlog items to meet the goal and create a Sprint Backlog based on a likely initial design and plan. Once the time-box for the Sprint Planning meeting is over, start the Sprint and continue to analyze, decompose, and create additional functionality during the Sprint.

C.

Continue the Sprint Planning meeting past its time-box until an adequate number of Product Backlog items are well enough understood for the Development Team to make a complete forecast. Then start the Sprint.

D.

Discuss in the upcoming Sprint Retrospective why this happened and what changes will make it less likely to recur.

E.

Ask everyone to take as much time as needed to analyze the Product Backlog first, and then reconvene another Sprint Planning meeting.

Buy Now
Question # 8

What are two effective ways for the Scrum Team to make non-functional requirements visible?

(choose the best two answers)

Options:

A.

Run the integration and regression tests before the end of the Sprint, and

capture the open work for the Sprint Backlog of the next Sprint.

B.

Put them on a separate list on the Scrum board, available for all to see.

C.

Add them to the Definition of Done so the work is taken care of every Sprint.

D.

Add them to the Product Backlog to ensure transparency.

Buy Now
Question # 9

A Scrum Master is keeping a list of open impediments, but it is growing and they have been able to resolve only a small portion of the impediments. Which two techniques would be most helpful in this situation?

(Choose two.)

Options:

A.

Discuss the impediments with the Development Team.

B.

Prioritize the list and work on them in order.

C.

Arrange a triage meeting with all project managers.

D.

Add each open impediment to the Product Backlog.

Buy Now
Question # 10

The Definition of Done serves which three purposes?

(choose the best three answers)

Options:

A.

Create a shared understanding of when work is complete.

B.

Guide the Developers on how many Product Backlog items to select for the

Sprint.

C.

Increase transparency.

D.

Describe the work that must be mostly done before the Sprint is allowed to end.

E.

Describe the purpose, Objective, and timebox Of each Scrum event.

Buy Now
Question # 11

A new Developer is having continuing conflicts with existing members or the scrum Team, which is impacting the delivery of the Increment It necessary, who is responsible for removing the Developer from the Scrum Team?

(choose the best answer)

Options:

A.

The Scrum Master is responsible, they remove impediments

B.

The Product Owner is responsible, they control the return on investment (ROI)

C.

The hiring manager is responsible, they hired the Developer

D.

The Scrum Team is responsible

Buy Now
Question # 12

Several Sprints into a project, the Product Owner tells the Scrum Master that a key stakeholder just started using the product. The stakeholder is unhappy with the quality of the product, and the Product Owner agrees with the stakeholder’s assessment that the quality is low. How should the Scrum Master respond to the Product Owner?

(choose the best two answers)

Options:

A.

Encourage the Product Owner to include quality specifications in the Product Backlog and to communicate the stakeholders ' concerns to the Developers.

B.

Bring the concern to the testers to improve how the Product is verified.

C.

Work with the Product Owner to understand their desired resolution and help formulate an approach for raising the concern with the Developers.

D.

Tell the Product Owner they have noted the concern and will raise this issue at the Sprint Retrospective.

E.

Explain to the Product Owner that it is up to the Developers to decide on acceptable quality standards.

Buy Now
Question # 13

When is it most appropriate for a Scrum Team to change the Definition of Done?

(choose the best answer)

Options:

A.

During Product Backlog refinement.

B.

During the Sprint Retrospective.

C.

During Sprint Planning.

D.

Prior to starting a new project.

Buy Now
Exam Code: PSM-I
Exam Name: Professional Scrum Master I
Last Update: Mar 15, 2026
Questions: 296
PSM-I pdf

PSM-I PDF

$25.5  $84.99
PSM-I Engine

PSM-I Testing Engine

$28.5  $94.99
PSM-I PDF + Engine

PSM-I PDF + Testing Engine

$40.5  $134.99