Question # 14

Who determines when it is appropriate to update the Sprint Backlog during a Sprint?

Options:

A.

The Project Manager.

B.

The Developers.

C.

The Scrum Team.

D.

The Product Owner.

Buy Now
Question # 15

The timebox for the Sprint Review is:

(choose the best answer)

Options:

A.

Any length of time needed.

B.

At the end of every Sprint.

C.

15 minutes.

D.

4 hours for a 4-week Sprint. Usually shorter for shorter Sprints.

Buy Now
Question # 16

The Developers have struggled to get all of their forecasted work done during the last three

Sprints. As a Product Owner what steps could you take to help the Developers improve their

ability to deliver a done Increment?

(choose the best two answers)

Options:

A.

Ask the Scrum Master to help the Developers learn techniques for improvingtheir ability to forecast work.

B.

The Product Owner can spend more time with the Developers.

C.

Ensure that all Developers are top performers.

D.

Add more people to the team so they can get more done.

Buy Now
Question # 17

Organizations should reduce their investment in a product when the product ' s:

(choose the best answer)

Options:

A.

Unrealized Value is very small.

B.

Current Value is very low.

C.

Current Value is very high.

D.

Unrealized Value is very large.

E.

None of the above.

Buy Now
Question # 18

Your stakeholders are very demanding and each of them has at least one feature that they say is essential for the next release. As the Product Owner, you have validated that the feature requests are all valid requests and would likely add value to your product. What should you do?

(choose the best answer)

Options:

A.

Wait until all essential features are complete before releasing the product.

B.

Pick the two most influential stakeholders and satisfy their needs, then release.

C.

Release when you can satisfy at least a single outcome, even though not all features are implemented.

D.

Escalate to the steering committee to make the call.

Buy Now
Question # 19

Who is accountable for clearly expressing Product Backlog items?

(choose the best answer)

Options:

A.

The Developers.

B.

The Scrum Master.

C.

The Scrum Master, or the Scrum Master may have the Developers help.

D.

The Product Owner, but the Product Owner may appoint a proxy on the Scrum Team to do the work.

E.

The Scrum Master, or the Scrum Master may have the Product Owner do it.

Buy Now
Question # 20

When should the Product Owner update the project plan?

(choose the best answer)

Options:

A.

After the Daily Scrum to ensure an accurate daily overview of project progress.

B.

The project plan must be updated prior to the Sprint Retrospective.

C.

The Product Backlog is the plan in Scrum. It is updated as new information andinsights emerge.

D.

Before the Sprint Planning to know how much work will have to be done in the Sprint.

Buy Now
Question # 21

Every Scrum Team must have a Product Owner and Scrum Master.

(Choose the best answer)

Options:

A.

Yes, and each Scrum Team ' s performance may be affected by how much they participate during the Sprint as a Scrum Master or Product Owner.

B.

No.

C.

Yes, and they must be 100% dedicated to each team.

Buy Now
Question # 22

You work for a large financial institution. Your products have many interdependencies: you have

mobile, web, and ATM product interfaces to financial products like savings, checking, spending,

electronic payments, credit cards, and investments. When any of these financial products

change, the changes ripple throughout the mobile, web, and ATM clients, and maintaining

consistency is challenging. What should you do to reduce this problem?

(choose the best answer)

Options:

A.

Form products that are as independent as possible and let each product determinetheir own release plans, but ensure coordination.

B.

Create a centralized, coordinated cross-product Development Plan to ensureconsistency.

C.

Appoint a Project Lead to oversee all the products.

D.

Ensure that the PMO manages the inter-product dependencies.

E.

All of the above.

Buy Now
Question # 23

Who is accountable for maintaining and communicating the Product Goal?

(choose the best answer)

Options:

A.

The Product Owner.

B.

The Developers.

C.

Executive Sponsors.

D.

Stakeholders.

E.

All of the above.

Buy Now
Exam Code: PSPO-II
Exam Name: Professional Scrum Product Owner™ II (PSPO 2)
Last Update: Jul 10, 2026
Questions: 92
PSPO-II pdf

PSPO-II PDF

$25.5  $84.99
PSPO-II Engine

PSPO-II Testing Engine

$28.5  $94.99
PSPO-II PDF + Engine

PSPO-II PDF + Testing Engine

$40.5  $134.99