What is an output of Control Scope?
Accepted deliverables
Work performance measurements
Requirements documentation
Work performance information
To which process is work performance information an input?
Contract administration
Direction and management of project execution
Create WBS
Qualitative risk analysis
Which process involves aggregating the estimated costs of the individual schedule activities or work packages?
Cost baseline
Cost forecasting
Cost variance
Cost budgeting
Which document formally authorizes a project?
The project charter
Project scope statement
The P'oject contract
Project closing document
The project charter is the formal document for authorizes a project.
What is the lowest level in a work breakdown structure?
Project task
w°rl< package
sow
None
A work package is the lowest level of a work breakdown structure.
From whom do you need to gain the formal acceptance at project closure?
The customer
The qualify director
Project management office
Project manager
need to gain this formal acceptance at project closure from the customer and sponsor.
Which of the following describes the purpose of the quality control process?
To identify quality requirements of the project
To identify ineffective processes and eliminate them
To assess performance and recommend necessary changes
To ensure quality standards are used
A weighting system is a tool for which area of procurement?
Plan contracting
Request seller responses
Select sellers
Plan purchase and acquisition
Which technique is utilized in the Schedule Control process?
Performance Measure
Baseline Schedule
Schedule Comparison
Variance Analysis
Which is the most risky phase of a project?
Planning
Closing
Execution
Control
The Planning phase is the phase with the least risk attached. The Execution phase of the project is when you are using your resources at their highest level .