Question # 24

What involves determining what quantities are to be used to perform project activities.

Options:

A.

Resource planning

B.

Estimate Costs

C.

Determine Budget

D.

Control Costs

Buy Now
Question # 25

Which statement is true about Bottom-up estimating?

Options:

A.

Estimating the cost of individual work items and then rolling up the costs to arrive at a project total.

B.

Uses the actual cost of a previous similar project as the basis for estimating the cost of the current project.

C.

Using project characteristics (or parameters) in a mathematical model to predict costs.

D.

Cost of quality can also be used to prepare the schedule activity cost estimate.

Buy Now
Question # 26

Adjusting Leads and Lags is a technique for:

Options:

A.

Develop Schedule

B.

Estimate Activity Durations

C.

Estimate Activity Resources

D.

Sequence Activities

Buy Now
Question # 27

Which of the following is a common characteristic of most project life cycle descriptions?

Options:

A.

Cost and staffing are low at the start, higher towards the end. and drop rapidly as the project nears completion.

B.

The probability of successfully completing the project is highest at the start of the project.

C.

Stakeholders have the most influence on the final characteristics of the product at the end of the project.

D.

a and b

Buy Now
Question # 28

Which of the following is the most important task of the project manager during the Execution and Control phase?

Options:

A.

Information management

B.

Maintain scope statement

C.

Maintain Charter

D.

Maintain Closing document

Buy Now
Question # 29

You are the project manager of a project and budgeted money to provide cash awards to team members that exceed expectations. A project team member that is motivated by the chance to earn cash reward can most accurately be explained by which theory

Options:

A.

Hierarchy of needs

B.

Expectancy theory

C.

Achievement theory

D.

Al1 of the above

Buy Now
Question # 30

To calculate the late start and late finish dates for a set of tasks , you must do :

Options:

A.

An analysis of the critical path

B.

A forwards pass

C.

A backwards pass

D.

a and g

Buy Now
Question # 31

What are common types of cost-reimbursable contracts?

Options:

A.

CPF

B.

CPFF

C.

CPIF

D.

Al1 of the above

Buy Now
Question # 32

Your company create software products, and introducing a new product. To determine the characteristics and features of the new product line, you will have to perform ________.

Options:

A.

Progressive elaboration

B.

Stake holder's review

C.

p'an project life cycle

D.

Fast backing

Buy Now
Question # 33

How many communication channels exist in a team of 10 members?

Options:

A.

45

B.

10

C.

30

D.

20

Buy Now
Exam Code: CA0-001
Exam Name: Certified Associate in Project Management (CAPM) Certification
Last Update: Aug 22, 2025
Questions: 525
CA0-001 pdf

CA0-001 PDF

$29.75  $84.99
CA0-001 Engine

CA0-001 Testing Engine

$33.25  $94.99
CA0-001 PDF + Engine

CA0-001 PDF + Testing Engine

$47.25  $134.99