Question # 34

Results from a process audit show that the requirements group does not control changes to its software specifications. Which of the following basic requirements should be added to the software configuration management (SCM) policy?

Options:

A.

SCM must be implemented throughout the project ' s lifecycle.

B.

SCM must be implemented for externally deliverable software products

C.

Responsibility- for SCM must be explicitly assigned for each project

D.

Each project must have an established repository for storing configuration items.

Buy Now
Question # 35

Which of the following testing methods is used to identify “dead code”?

Options:

A.

Black-box

B.

Simulation

C.

White-box

D.

Regression

Buy Now
Question # 36

Which of the following is a responsibility of a lead auditor?

Options:

A.

Submitting the audit report

B.

Determining the scope of the audit

C.

Determining the corrective actions required

D.

Performing the initial review of the quality system

Buy Now
Question # 37

A software development team has just completed the planning phase of a project when management recommends additional requirements. The team’s best response to this request would be to

Options:

A.

perform an impact analysis and adjust the plan accordingly

B.

agree to introduce the new requirements on the next version release

C.

outsource the new requirements to a subcontractor and manage it as a subordinate project

D.

adjust the resources and budget to maintain the project’s schedule and due date with the new requirements

Buy Now
Question # 38

In lean software development extra features should be identified as

Options:

A.

potential re-use elements

B.

an internal cost of quality

C.

defects

D.

waste

Buy Now
Question # 39

When lines of code are used as a software metric, counting rules must be based on

Options:

A.

criteria established by the requirements

B.

predefined criteria

C.

a line-by-line code review

D.

module interfaces

Buy Now
Question # 40

Which of the following can be used to assess the impact of a proposed software change?

Options:

A.

Traceability matrix

B.

Regression testing

C.

Baseline audit

D.

Defect rate

Buy Now
Question # 41

Which of the following actions can a company take to reduce the risk associated with integrating a commercial off-the-shelf (COTS) spreadsheet package into its own software product?

Options:

A.

Require the vendor to adhere to the keens mg agreement for product fixes.

B.

Audit the vendor ' s quality- system.

C.

Require the vendor to place the object code into escrow.

D.

Test the product to determine whether it satisfies critical functions.

Buy Now
Question # 42

In specifying a software requirement, it is important to consider how the requirement might be

Options:

A.

referenced

B.

documented

C.

coded

D.

validated

Buy Now
Question # 43

A software hazard analysis should be conducted in order to

Options:

A.

identify and evaluate the level of risk

B.

predict when the hazard will occur

C.

calculate the cost of correcting the problem

D.

comply with government regulations

Buy Now
Exam Code: CSQE
Exam Name: Certified Software Quality Engineer Exam
Last Update: Jun 21, 2026
Questions: 280
CSQE pdf

CSQE PDF

$25.5  $84.99
CSQE Engine

CSQE Testing Engine

$28.5  $94.99
CSQE PDF + Engine

CSQE PDF + Testing Engine

$40.5  $134.99