Question # 14

Fill in the blank with the appropriate word.

______refers to conveying a message from an individual person to another or to several people, whether verbally or non-verbally

Options:

Buy Now
Question # 15

You are the project manager for your organization and are planning the project work with your project team. You are currently breaking down the project scope into work packages to determine an accurate time and cost estimate. What document are you and the project team creating?

Options:

A.

Project management plan

B.

Work breakdown structure

C.

Code of accounts

D.

Project scope

Buy Now
Question # 16

Which of the following are the types of casual/econometric forecasting methods?

Each correct answer represents a complete solution. Choose all that apply.

Options:

A.

ARIMA

B.

Econometrics

C.

ARMA

D.

Scenario building

Buy Now
Question # 17

You have been assigned as the Project Manager for a new project that involves development of a new interface for your existing time management system. You know that developers are available in your organization, and would like to use them. However, your program manager thinks that an outside company needs to be engaged to complete this development. Which of the following will help you to convince your project manager to use the internal resources?

Options:

A.

Expert Judgment

B.

Make or buy analysis

C.

Survey Questionnaire

D.

Issue log

Buy Now
Question # 18

Which of the following processes is described in the statement below?

"It is involved with many kinds of process design and with implementation and improvement to the IT infrastructure and service processes."

Options:

A.

Risk Management

B.

Change Management

C.

Configuration Management

D.

Continual Process Improvement Management

Buy Now
Question # 19

You work as a project manager for PassGuide Inc. Your project was baselined at 8 hours, but 11 hours have been spent and the estimate to complete is 1 additional hour. The project must have been completed already. An hourly rate of $100 per hour is provided. Which of the following is the planned value (PV) for the project?

Options:

A.

$500

B.

$700

C.

$800

D.

$600

Buy Now
Question # 20

Which of the following is described in the statement below?

"It is defined as the work element that must be carefully monitored, documented, and managed to make the success of an organization, program, or project."

Options:

A.

Red rated activity

B.

High alert activity

C.

Action items

D.

Critical activity

Buy Now
Question # 21

You are a project manager for your organization. Your organization completes projects for other companies and your project has just ended. Although you were serving in a contractual relationship for your company what should you do with the project records for the project you've completed for another entity?

Options:

A.

The project information should be archived at your organization.

B.

The project information should be archived at your organization and at the client's organization.

C.

The project information should be destroyed.

D.

The project information should stay with the company you completed the project for.

Buy Now
Question # 22

Which of the following management skills is described in the statement below?

"It is a strategy of sharing power and relying on interpersonal skill to get others to cooperate towards common goals."

Options:

A.

Communication

B.

Motivation

C.

Influencing

D.

Negotiation

Buy Now
Question # 23

Jeff works as a project manager for PassGuide Inc. He has to adjust the amount of time between two activities. He wants to delay the start of the second activity by 14 hours. Which of the following scheduling components will Jeff add to the second activity?

Options:

A.

Project slack

B.

Project float

C.

Lag time

D.

Lead time

Buy Now
Exam Code: GCPM
Exam Name: GIAC Certified Project Manager Certification Practice Test
Last Update: Aug 24, 2025
Questions: 397
GCPM pdf

GCPM PDF

$25.5  $84.99
GCPM Engine

GCPM Testing Engine

$28.5  $94.99
GCPM PDF + Engine

GCPM PDF + Testing Engine

$40.5  $134.99