Weekend Sale 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: Board70

GCPM Exam Dumps - GIAC Certification Questions and Answers

Question # 24

Fill in the blank with the appropriate term.

A______ specifies the sequence and number of letters or numbers required for each level and the symbol separating the levels in a work breakdown structure (WBS) code or a custom outline code.

Options:

Buy Now
Question # 25

Which of the following are outputs of the perform quality assurance process?

Each correct answer represents a complete solution. Choose all that apply.

Options:

A.

Organizational process assets update

B.

Change requests

C.

Work performance information

D.

Project management plan updates

Buy Now
Question # 26

Which of the following elements facilitates people to know large amounts of information as a picture rather than a table of names and numbers?

Options:

A.

Risk register

B.

Stakeholder register

C.

Project charter

D.

Organization chart

Buy Now
Question # 27

You are the project manager of a large construction project. Part of the project involves the wiring of the electricity in the building your project is creating. You and the project team determine the electrical work is too dangerous to perform yourself so you hire an electrician to perform the work for the project. This is an example of what type of risk response?

Options:

A.

Mitigation

B.

Acceptance

C.

Transference

D.

Avoidance

Buy Now
Question # 28

You work as a project manager for PassGuide Inc. Your project has a budget of $545,000 and is expected to last 12 months. You have identified several risk events and created risk response plans for your project. In which of the following process groups will you be able to implement risk response plans?

Options:

A.

Planning

B.

Initiating

C.

Executing

D.

Monitoring and controlling

Buy Now
Question # 29

Gary has identified a project risk that could injure project team members. He does not want to accept any risk where someone could become injured on this project so he hires a professional vendor to complete this portion of the project work. This workaround to the risk event is known as what type of risk response?

Options:

A.

Mitigation

B.

Acceptance

C.

Transference

D.

Avoidance

Buy Now
Question # 30

You are the project manager for your organization and would like to use a time and materials contract for a small project. What must a time and materials contract have to safeguard the project?

Options:

A.

Terms for payment

B.

Approval from the project sponsor

C.

An approved vendor by a leading trade organization

D.

A not-to-exceed clause

Buy Now
Question # 31

Sam is the project manager for his organization. His project is not doing well on project schedule performance, and management wants him to predict how the project schedule and cost will end. Management has asked Sam to report and forecast his project's performance based on the Delphi Method, scenario building, technology forecasting, and to forecast by analogy. What forecasting method is management asking Sam to use?

Options:

A.

Earned value management method

B.

Time series methods

C.

Causal/econometric methods

D.

Judgmental methods

Buy Now
Question # 32

Which of the following processes formally permits the initiation of a project and marks the kickoff for all consequent development activities to begin?

Options:

A.

Develop project charter

B.

Develop project management plan

C.

Develop project scope statement

D.

Develop project team

Buy Now
Question # 33

You are the project manager of the NNN Project. Stakeholders in the two-year project have requested to send status reports to them via email every week. You have agreed and are sending the reports on each Thursday. After six months of the project, the stakeholders are pleased with the project progress and they would like you to reduce the status reports to every two weeks. What process will examine the change to this project process and implement it in the project?

Options:

A.

Project change control process

B.

Configuration management

C.

Perform integrated change control process

D.

Communications management

Buy Now
Exam Code: GCPM
Exam Name: GIAC Certified Project Manager Certification Practice Test
Last Update: Aug 24, 2025
Questions: 397
GCPM pdf

GCPM PDF

$25.5  $84.99
GCPM Engine

GCPM Testing Engine

$28.5  $94.99
GCPM PDF + Engine

GCPM PDF + Testing Engine

$40.5  $134.99