Weekend Special Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: bigdisc65

ISTQB-CTFL Exam Dumps - ISTQB Foundation Level Questions and Answers

Question # 74

Which of the following statements about test estimation approaches is CORRECT?

Options:

A.

The Wideband Delphi estimation technique is an example of the risk-based approach

B.

The Wideband Delphi estimation technique is an example of the expert-based approach

C.

Bumdown charts used in Agile development is an example of the risk-based approach

D.

Burndown charts used in Agile development is an example of the expert-based approach

Buy Now
Question # 75

An agile software development organization has recently hired a senior tester. The organization has distributed teams spread across time zones. They need to share test status with various stakeholders including upper management and customers at a regular interval. Which of the following statements seems to be correct with regards to the communication?

Options:

A.

Since the stakeholders include customers frequent informal communication without a specific frequency works better.

B.

Agile nature of the project means very less documentation and hence the status need not be documented and shared in a formal manner

C.

Since the stakeholders include upper management, formal reports delivered face-to-face are critical.

D.

Distributed nature of teams working in various time zones means email communication will work better

Buy Now
Question # 76

Which of the following is the main benefit of a configuration management of testware?

Options:

A.

All testware is backed up with restore option, including incident reports and change requests. B. The testware can be traced to information in requirements tools and to the bug tracking system.

B.

All testware items are identified, version controlled, tracked tor changes with relation to each other

C.

There is an easy way to assess the level to test coverage provided by the existing tests

Buy Now
Question # 77

Which of the following statements is the BEST example of non-functional testing?

Options:

A.

Tests which capture the time it takes to save a file

B.

Tests which calculate overtime pay for those employees entitled to such

C.

Tests related to "what" the system should do

D.

Tests based on the internal structure of a component or system

Buy Now
Question # 78

Which one of the following is a typical entry criteria for testing?

Options:

A.

Planned tests have been executed.

B.

Availability of testable requirements.

C.

The number of unresolved defects is within an agreed limit.

D.

The number of estimated remaining defects is sufficiently low.

Buy Now
Question # 79

Which of the following tools is most likely to detect defects in functions or methods in source code?

Options:

A.

configuration management tool

B.

unit test framework tool

C.

test design tool

D.

monitoring tool

Buy Now
Question # 80

The following diagram displays the logical dependencies between requirements and the individual requirement priorities. For example, "R2->R3" means that R3 is dependent on R2. Priority is indicated by the number next to the letter ”P" i.e. P1 has a higher priority than P2.

Which one of the following options best describes the test execution sequence using both requirement dependency and priority

Options:

A.

R2. R1, R3. R4. R5, R6. R7, R8.

B.

R1, R2, R3, R4, R5, R6, R7, R8.

C.

R2, R4. R8, R5, R1, R6, R3, R7.

D.

. R2, R1,R3,R7,R6,R5,R4,R8.

Buy Now
Question # 81

As a tester, as part of a V-model project, you are currently executing some tests aimed at verifying if a mobile app asks the user to grant the proper access permissions during the installation process and after the installation process. The requirements specification states that in both cases the app shall ask the user to grant access permissions only to the camera and photos stored on the device. However, you observe that the app also asks the user to grant access permission to all contacts on the device. Consider the following items:

[I]. Test environment

[ii]. Expected result

[iii]. Actual result.

[IV] Test level.

[V]. Root cause.

Based on only the given information, which of the items listed above, are you able to CORRECTLY specify in a defect report?

Options:

A.

[l] and [IV]

B.

[ii] and [III].

C.

[ii], [iii] and [v]

D.

[ii], [IV] and [V].

Buy Now
Question # 82

Which of the following statements about branch coverage is true?

Options:

A.

The minimum number of test cases needed to achieve full branch coverage, is usually lower than that needed to achieve full statement coverage

B.

If full branch coverage has been achieved, then all unconditional branches within the code have surely been exercised

C.

If full branch coverage has been achieved, then all combinations of conditions in a decision table have surely been exercised

D.

Exercising at least one of the decision outcomes for all decisions within the code, ensures achieving full branch coverage

Buy Now
Question # 83

Which of the following statements is CORRECT about White-box testing?

Options:

A.

White-box testing helps find defects even when specifications are vague because it takes into account the code

B.

box testing helps find defects because it provides for requirements based coverage

C.

White-box testing helps find defects because it focuses on defects rather than failures

D.

White-box testing helps find defects because they can be used to measure statement coverage

Buy Now
Exam Code: ISTQB-CTFL
Exam Name: ISTQB Certified Tester Foundation Level (CTFL v4.0)
Last Update: Sep 16, 2025
Questions: 361
ISTQB-CTFL pdf

ISTQB-CTFL PDF

$29.75  $84.99
ISTQB-CTFL Engine

ISTQB-CTFL Testing Engine

$33.25  $94.99
ISTQB-CTFL PDF + Engine

ISTQB-CTFL PDF + Testing Engine

$47.25  $134.99