Blakenall District Hospital (BDH) is a large hospital that is a major part of the government’s health service. Purchasing staff are in the habit of placing many long-term contracts with suppliers and sub-contractors. Whilst these contracts are usually carried out successfully, prices are often paid that are well over budget. The purchasing manager is concerned to find that, in some cases, members of staff are forcing suppliers to accept fixed price contracts. The policy hascaused several problems such as some suppliers refusing to deal with BDH and a few going out of business mid-way through performing a contract with BDH. This is due to fluctuating market prices of materials. The procurement manager suggests supplier to adopt variable pricing arrangement with price index. Is this a right course of action?
Rochdale Ltd is looking for a new IT system to automate some of its operations. In designing the specification, procurement manager supposes that it should be done solely by the IT department who have deep expertise on this matter. Is procurement manager’s opinion appropriate?
Which of the following is the type of insurance that cover the liabilities of service provider such as legal advice, accountancy, technical designs, etc?
In what way might a contract clause be used to stop the supplier from making unwarranted price increases during the term of the contract?
A Service Level Agreement (SLA) is a formal statement of performance. Which of the following are aspects of a service level agreement?
A force majeure clause
Key performance indicators
A penalty clause for non-performance
The legal jurisdiction of the contract
GPP, the employer, and Prosolia UK, the contractor, entered into five EPC contracts for the development of five different solar power generation plants in the United Kingdom. Four out of the five developments failed to be commissioned by the relevant due dates, with the delays ranging from 44 to 285 days.
Among other claims, GPP, acting through its two investment vehicles, claimed liquidated damages of £500 per day in all four contracts for Prosolia UK's failure to achieve completion of the plants by the due date. The liquidated damages claimed amounted to £1,804,221 across the four delayed contracts.
Prosolia, alongside various other defences, raised the defence that the liquidated damages provision in each contract was a penalty, and therefore unenforceable against it. Is Prosolia contractually obliged to make the payment to the plaintiff?
Buyer D agrees a contract with Supplier C which includes the words 'to be agreed' in relation to the date for delivery of the goods. At the time of the contract, Buyer D is aware that the goods take two days to produce and one day to deliver. Buyer D contacts the supplier one week later, requesting the goods be delivered the following day. Supplier C is unable to deliver the next day but rather delivers the goods three days later. Is it the case that Buyer D can legally refuse to pay for the goods because Supplier C is in breach of contract?
Which of the following are typically included in an SLA? Select TWO that apply:
Which of the following are likely to be advantages of using invitation to tender? Select TWO that apply:
Short turnaround times
Which of the following can be considered as implied terms in a contract?
1. Case law
2. Statute
3. Trade custom
4. A term can never be implied, it must always be expressed by the parties