Weekend Special Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: bigdisc65

L4M3 Exam Dumps - CIPS Level 4 Diploma in Procurement and Supply Questions and Answers

Question # 24

Blakenall District Hospital (BDH) is a large hospital that is a major part of the government’s health service. Purchasing staff are in the habit of placing many long-term contracts with suppliers and sub-contractors. Whilst these contracts are usually carried out successfully, prices are often paid that are well over budget. The purchasing manager is concerned to find that, in some cases, members of staff are forcing suppliers to accept fixed price contracts. The policy hascaused several problems such as some suppliers refusing to deal with BDH and a few going out of business mid-way through performing a contract with BDH. This is due to fluctuating market prices of materials. The procurement manager suggests supplier to adopt variable pricing arrangement with price index. Is this a right course of action?

Options:

A.

No, variable pricing would only benefit the suppliers

B.

Yes, this type of arrangement would provide absolute certainty when budgeting

C.

Yes, this pricing arrangement would reimburse the fluctuation of material prices

D.

No, price adjustment should be applied to short-term supply contract only (3-month duration or less)

Buy Now
Question # 25

Rochdale Ltd is looking for a new IT system to automate some of its operations. In designing the specification, procurement manager supposes that it should be done solely by the IT department who have deep expertise on this matter. Is procurement manager’s opinion appropriate?

Options:

A.

No, because challenging the user's demand is the role of procurement

B.

Yes, because designing complex specification would waste procurement manager’s time

C.

Yes, because procurement professional has no expertise in IT sector

D.

No, because designing complex specification could only be outsourced

Buy Now
Question # 26

Which of the following is the type of insurance that cover the liabilities of service provider such as legal advice, accountancy, technical designs, etc?

Options:

A.

PII

B.

Product liability

C.

Employer’s liability

D.

Public liability

Buy Now
Question # 27

In what way might a contract clause be used to stop the supplier from making unwarranted price increases during the term of the contract?

Options:

A.

The buyer deletes any contract clauses that may refer to stage payments

B.

The buyer inserts a contract clause that stipulates the invoice payment dates

C.

The buyer inserts a price adjustment clause in the contract

D.

The buyer deletes any contract clauses that may refer to price increases

Buy Now
Question # 28

A Service Level Agreement (SLA) is a formal statement of performance. Which of the following are aspects of a service level agreement?

A force majeure clause

Key performance indicators

A penalty clause for non-performance

The legal jurisdiction of the contract

Options:

A.

2 and 3 only

B.

2 and 4 only

C.

1 and 2 only

D.

1 and 4 only

Buy Now
Question # 29

GPP, the employer, and Prosolia UK, the contractor, entered into five EPC contracts for the development of five different solar power generation plants in the United Kingdom. Four out of the five developments failed to be commissioned by the relevant due dates, with the delays ranging from 44 to 285 days.

Among other claims, GPP, acting through its two investment vehicles, claimed liquidated damages of £500 per day in all four contracts for Prosolia UK's failure to achieve completion of the plants by the due date. The liquidated damages claimed amounted to £1,804,221 across the four delayed contracts.

Prosolia, alongside various other defences, raised the defence that the liquidated damages provision in each contract was a penalty, and therefore unenforceable against it. Is Prosolia contractually obliged to make the payment to the plaintiff?

Options:

A.

No, the amount claimed is too excessive and it may put Prosolia into insolvency. The clause must be void

B.

No, the clause must be treated as a penalty clause which is unenforceable in UK

C.

Yes, the amount is a reward to the employer as they have supervised and monitored the projects

D.

Yes, the clause is a genuine estimate of possible losses that GPP may have suffered and therefore, it is enforceable.

Buy Now
Question # 30

Buyer D agrees a contract with Supplier C which includes the words 'to be agreed' in relation to the date for delivery of the goods. At the time of the contract, Buyer D is aware that the goods take two days to produce and one day to deliver. Buyer D contacts the supplier one week later, requesting the goods be delivered the following day. Supplier C is unable to deliver the next day but rather delivers the goods three days later. Is it the case that Buyer D can legally refuse to pay for the goods because Supplier C is in breach of contract?

Options:

A.

Yes, because the delivery date is an express term within the contract

B.

Yes, because the goods should have been delivered within three days

C.

No, because the goods were delivered within a reasonable time

D.

No, because there is a contract in place and the delivery date does not matter

Buy Now
Question # 31

Which of the following are typically included in an SLA? Select TWO that apply:

Options:

A.

Requirements for packaging

B.

Service definition

C.

KPI detailsCorrect)

D.

Code of conduct

E.

Product's lifespan

Buy Now
Question # 32

Which of the following are likely to be advantages of using invitation to tender? Select TWO that apply:

Short turnaround times

Options:

A.

Quick implementation

B.

Driving forward planning culture

C.

Lower administration costs

D.

Reducing risks of bribery and corruption

Buy Now
Question # 33

Which of the following can be considered as implied terms in a contract?

1. Case law

2. Statute

3. Trade custom

4. A term can never be implied, it must always be expressed by the parties

Options:

A.

1,3 and 4 only

B.

1, 2 and 3 only

C.

1, 2 and 4 only

D.

2, 3 and 4 only

Buy Now
Exam Code: L4M3
Exam Name: Commercial Contracting
Last Update: Jun 14, 2025
Questions: 196
L4M3 pdf

L4M3 PDF

$29.75  $84.99
L4M3 Engine

L4M3 Testing Engine

$33.25  $94.99
L4M3 PDF + Engine

L4M3 PDF + Testing Engine

$47.25  $134.99