Question # 4

ERV systems shall not be installed in which of the following except:

Options:

A.

systems utilizing coil-type exchangers.

B.

common exhaust systems for clothes dryers.

C.

exhaust systems emitting corrosive materials.

D.

equipment designed to assist in the evacuation of occupants.

Buy Now
Question # 5

Exposed solar thermal equipment protected by motor vehicle impact may be installed at what height?

Options:

A.

Directly on finished floor

B.

6 feet above finished floor

C.

18 inches above finished floor

D.

48 inches above finished floor

Buy Now
Question # 6

Where located on a roof with a 5:12 slope, a level platform shall be provided along the access panel of the furnace at least _____ inches wide.

Options:

A.

[option text not fully visible in the material you sent]

B.

24

C.

30

D.

36

Buy Now
Question # 7

Exhaust is required for which of the following areas?

Options:

A.

Gambling casinos

B.

Office break rooms

C.

High school locker rooms

D.

Prison guard stations

Buy Now
Question # 8

Floor furnaces shall not be closer than _____ inches to the ground.

Options:

A.

[option text not fully visible in the material you sent]

B.

[option text not fully visible in the material you sent]

C.

[option text not fully visible in the material you sent]

D.

12

Buy Now
Question # 9

Exhibit:

CEF-5 is a ceiling exhaust fan manufactured by:

Options:

A.

G.E.

B.

Carnes

C.

Markel

D.

Nutone

Buy Now
Question # 10

An equipment shutoff valve shall be in the same room and not more than how many feet away from the appliance?

Options:

A.

6

B.

7

C.

8

D.

9

Buy Now
Question # 11

Exhaust outlets that terminate at a temperature exceeding 600°F shall be designed as a:

Options:

A.

Class I duct.

B.

Class II duct.

C.

Class III duct.

D.

single-wall metal chimney.

Buy Now
Question # 12

Shutoff valves in plastic pipe ground-source heat pump loop systems shall be installed on both sides of which one of the following?

Options:

A.

Expansion tanks

B.

Heat-fusion joints

C.

Change-in-material joints

D.

Pressure-reducing valves

Buy Now
Question # 13

The minimum rise required for a 10-foot run of vent connector is _____ inches.

Options:

A.

1-1/4

B.

1-1/2

C.

2

D.

2-1/2

Buy Now
Exam Code: M2
Exam Name: Commercial Mechanical Inspector
Last Update: Apr 5, 2026
Questions: 50
M2 pdf

M2 PDF

$25.5  $84.99
M2 Engine

M2 Testing Engine

$28.5  $94.99
M2 PDF + Engine

M2 PDF + Testing Engine

$40.5  $134.99