Weekend Special - 75% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: certbig75

PRINCE2-7-Practitioner Exam Dumps - PRINCE2 Certification Questions and Answers

Question # 14

During stage 1, the City Council purchasing team must prepare the contract that will govern BuildyBrick’s later design and construction work. The project manager agrees with the purchasing team the products, time and cost for this work package.

Which practice is being applied through the ‘controlling a stage’ process?

Options:

A.

Business case

B.

Organization

C.

Plans

D.

Quality

Buy Now
Question # 15

QUALITY

Here are three items of information relating to the testing of the solar panels during stage 4.

Under which heading of the quality register (A–E) should each item be recorded?

Choose only ONE heading for each item. Each heading can be used once, more than once, or not at all.

Options:

A.

Quality method

B.

Dates

C.

Responsibilities

D.

Result

E.

Records

Item 1:

Specialist equipment will be used to verify that the energy output from the solar panels meets the applicable industry standards.

Item 2:

The solar-panel testing will be completed in week 2 of stage 4, one week after the security-system testing.

Item 3:

Testing found that one solar panel did not meet the required energy-output standard.

Buy Now
Question # 16

During stage 2, the Heritage Director, acting as senior user, reviews the design and raises a concern that the previously requested heritage trail has not been addressed.

Is this an appropriate use of the ‘give ongoing direction’ activity, and why?

Options:

A.

Yes, because a project board member may raise concerns and provide ongoing direction within the authority delegated to the board

B.

Yes, because the senior user has an obligation to formally approve key specialist products produced during stages 2 and 3 as a standard action within the ‘give ongoing direction’ activity

C.

No, because the ‘give ongoing direction’ activity is only triggered when the project manager proactively requests a review by the project board, not when individual board members identify concerns independently

D.

No, because the Heritage Director should first seek the agreement of the full project board before raising individual concerns, to ensure a unified project board position is presented to the project manager

Buy Now
Question # 17

Before a BuildyBrick subcontractor begins testing the utilities and systems, the proposed team plan and the commitment to deliver the testing work package must be agreed.

Which role agrees to carry out the work package in the ‘managing product delivery’ process?

Options:

A.

Project manager

B.

Team manager

C.

Senior supplier

D.

Project support

Buy Now
Question # 18

A product description contains only the following quality specification for the car-parking component: “The shopping centre will include an underground car park.”

Is this an effective application of the quality practice, and why?

Options:

A.

Yes, because confirming that a car park exists completely specifies its required quality

B.

Yes, because the statement provides sufficient information to confirm whether the required component has been delivered

C.

No, because all details of the car park should be recorded only in the quality management approach

D.

No, because the product description needs sufficiently detailed, measurable quality specifications and tolerances to support planning and verification

Buy Now
Question # 19

During a periodic evaluation of the security-system work package, the team manager reviews the work package description, team plan, and the related issue, risk, quality, product, and lessons information. Missing electrical cabling means that installation is now forecast to finish one week late, exceeding the work-package time tolerance.

The team manager raises the issue with the project manager and reports the current status in the checkpoint report. Is this an appropriate application of the ‘evaluate a work package’ activity, and why?

Options:

A.

Yes, because evaluation confirms that completed quality activities are recorded and that the current status is understood by the relevant parties

B.

Yes, because the team manager should review the work-package information, report progress for the agreed period, and notify the project manager when a tolerance is forecast to be exceeded

C.

No, because only the project manager may evaluate the status of a work package and decide what it should report

D.

No, because a forecast work-package tolerance breach should be reported directly to the project board in an exception report

Buy Now
Exam Name: PRINCE2 Project Management Practitioner (Version 7)
Last Update: Oct 3, 2026
Questions: 56
PRINCE2-7-Practitioner pdf

PRINCE2-7-Practitioner PDF

$21.25  $84.99
PRINCE2-7-Practitioner Engine

PRINCE2-7-Practitioner Testing Engine

$23.75  $94.99
PRINCE2-7-Practitioner PDF + Engine

PRINCE2-7-Practitioner PDF + Testing Engine

$33.75  $134.99