As stage 3 approaches its end, the project manager seeks supplier-related advice from the CEO of BuildyBrick, acting in the senior supplier interest, about planning the testing and inspections in stage 4.
Under which ‘directing a project’ activity is this informal consultation provided?
PLANS
Here are three items of information included in the stage 2 plan.
Under which heading (A–F) should each item be recorded?
Choose only ONE heading for each item of information. Each heading may be used once, more than once, or not at all.
During the ‘starting up a project’ process, the Business Opportunities Director appoints the Regeneration Manager as project manager and states that the portfolio’s standard role description will apply without discussion. The Regeneration Manager asks to confirm the responsibilities, but the Director refuses because the project is urgent.
Is the refusal an appropriate application of the ‘define roles, responsibilities and relationships’ principle, and why?
BuildyBrick is demobilizing after delivering the shopping centre on time and within budget. Before the remaining supplier personnel leave, the project manager checks that the Council’s operations and facilities teams are ready to receive, operate and maintain the completed centre.
Why is this an appropriate application of the ‘confirm project acceptance’ activity?
ISSUES
During stage 1, BuildyBrick was appointed by the procurement team manager as the main contractor for the project. The project is now in stage 3 and BuildyBrick is part way through the site preparation. Following an environmental survey report, BuildyBrick will have to delay the site clearance by several weeks to enable protected amphibians to be relocated. There are two options to deal with this issue. The first is to wait for BuildyBrick to clear the site, but this will take longer. The second is to hire an additional contractor to clear the site more quickly, but this will cost more. Both of these options can be completed within cost and time tolerances, but appointing an additional contractor is beyond the project manager’s delegated authority.
Here are three actions related to the resolution of this issue.
Which role (A–E) should be responsible for each action?
Choose only ONE role for each action. Each role can be used once, more than once, or not at all.
ORGANIZATION
Use the ‘Additional Information’ in the Scenario Booklet to answer this question.
Here are three roles relating to the LouisShopping Project.
Which individual (A–E) would be MOST appropriate for each role according to the ‘organization’ practice?
Choose only ONE individual for each role. Each individual can be used once, more than once, or not at all.
During stage 3, the foundations team manager tells the project manager that the completed foundations may have changed rainwater flow onto a neighbouring property. The project manager notes the concern in the project log but dismisses it without assessment and instructs the team to continue because the design has planning approval.
Is this an appropriate application of the ‘capture issues and risks’ activity, and why?
Before accepting the stage 2 design work package, the BuildyBrick team manager needs to determine how the design team will be organized and controlled and whether the work can be achieved within the stated constraints.
During which ‘managing product delivery’ activity should this be done?
The Chief Technology Officer is an influential stakeholder who strongly supports several unproven technologies for the shopping centre. Concerned about delivery risk and reputation, the project executive asks the project manager to limit the CTO’s contact with the project team and other stakeholders.
Is this an appropriate approach to leading successful change, and why?
At the start of stage 3, an approved request for change adds a promotional video to the stage. BuildyBrick has agreed to produce it, a product description has been prepared, and the project manager now needs to instruct the BuildyBrick team manager to begin the work.
During which ‘controlling a stage’ activity should this instruction be given?