Question # 4

As stage 3 approaches its end, the project manager seeks supplier-related advice from the CEO of BuildyBrick, acting in the senior supplier interest, about planning the testing and inspections in stage 4.

Under which ‘directing a project’ activity is this informal consultation provided?

Options:

A.

Authorize a stage or exception plan

B.

Give ongoing direction

C.

Authorize initiation

D.

Authorize the project

Buy Now
Question # 5

PLANS

Here are three items of information included in the stage 2 plan.

Under which heading (A–F) should each item be recorded?

Choose only ONE heading for each item of information. Each heading may be used once, more than once, or not at all.

Options:

A.

Dependencies

B.

Planning assumptions and prerequisites

C.

Products to be delivered

D.

Budget

E.

Tolerances

F.

Monitoring, control and reporting arrangements

Item 1:

The plan assumes that limited familiarity with new sustainable technologies will increase the likelihood of design errors, so additional time has been allowed for quality control.

Item 2:

During stage 2, the project manager will send the project board a summary of design progress every two weeks.

Item 3:

Stage 2 will produce archi

Buy Now
Question # 6

During the ‘starting up a project’ process, the Business Opportunities Director appoints the Regeneration Manager as project manager and states that the portfolio’s standard role description will apply without discussion. The Regeneration Manager asks to confirm the responsibilities, but the Director refuses because the project is urgent.

Is the refusal an appropriate application of the ‘define roles, responsibilities and relationships’ principle, and why?

Options:

A.

Yes, because standardized portfolio role descriptions give every project manager a consistent and well-understood baseline of responsibilities, removing the need for individual discussion

B.

Yes, because it is the project executive’s responsibility to appoint the project manager and establish their responsibilities as part of the ‘starting up a project’ process

C.

No, because each project manager must have a clear understanding of their own individual responsibilities and formally accept those responsibilities before commencing project work

D.

No, because it is the portfolio manager’s role, rather than the project executive’s, to define the project manager’s responsibilities for projects within the portfolio

Buy Now
Question # 7

BuildyBrick is demobilizing after delivering the shopping centre on time and within budget. Before the remaining supplier personnel leave, the project manager checks that the Council’s operations and facilities teams are ready to receive, operate and maintain the completed centre.

Why is this an appropriate application of the ‘confirm project acceptance’ activity?

Options:

A.

Because the project manager should complete the end project performance assessment before any supplier demobilizes

B.

Because the project manager should arrange a celebration before the contractor leaves the site

C.

Because all project information should be archived before the completed project product is accepted

D.

Because the project manager should confirm that handover to the operational and maintenance environment is complete

Buy Now
Question # 8

ISSUES

During stage 1, BuildyBrick was appointed by the procurement team manager as the main contractor for the project. The project is now in stage 3 and BuildyBrick is part way through the site preparation. Following an environmental survey report, BuildyBrick will have to delay the site clearance by several weeks to enable protected amphibians to be relocated. There are two options to deal with this issue. The first is to wait for BuildyBrick to clear the site, but this will take longer. The second is to hire an additional contractor to clear the site more quickly, but this will cost more. Both of these options can be completed within cost and time tolerances, but appointing an additional contractor is beyond the project manager’s delegated authority.

Here are three actions related to the resolution of this issue.

Which role (A–E) should be responsible for each action?

Choose only ONE role for each action. Each role can be used once, more than once, or not at all.

Options:

A.

Project executive

B.

Senior user

C.

Senior supplier

D.

Project assurance

E.

Project manager

Action 1:

Review the issue report and decide which response should be authorized.

Action 2:

After the decision is made, update the issue record with the selected response and decision.

Action 3:

Once the appointment is authorized, confirm that the supplier resources required for the additional site-clearance work can be provided.

Buy Now
Question # 9

ORGANIZATION

Use the ‘Additional Information’ in the Scenario Booklet to answer this question.

Here are three roles relating to the LouisShopping Project.

Which individual (A–E) would be MOST appropriate for each role according to the ‘organization’ practice?

Choose only ONE individual for each role. Each individual can be used once, more than once, or not at all.

Options:

A.

Regeneration Manager

B.

Regeneration Officer

C.

Chief Technology Officer

D.

Heritage Manager

E.

Portfolio Director

Roles:

Project support

User assurance

Senior supplier

Buy Now
Question # 10

During stage 3, the foundations team manager tells the project manager that the completed foundations may have changed rainwater flow onto a neighbouring property. The project manager notes the concern in the project log but dismisses it without assessment and instructs the team to continue because the design has planning approval.

Is this an appropriate application of the ‘capture issues and risks’ activity, and why?

Options:

A.

Yes, because recording the concern in the project log is sufficient before allowing delivery to continue

B.

Yes, because the project manager may dismiss an informally raised concern without further investigation

C.

No, because the project manager should assess an informally raised concern before deciding what action to take

D.

No, because the team manager should report the concern only in the next scheduled checkpoint report

Buy Now
Question # 11

Before accepting the stage 2 design work package, the BuildyBrick team manager needs to determine how the design team will be organized and controlled and whether the work can be achieved within the stated constraints.

During which ‘managing product delivery’ activity should this be done?

Options:

A.

Notify work package completion

B.

Execute a work package

C.

Evaluate a work package

D.

Accept a work package

Buy Now
Question # 12

The Chief Technology Officer is an influential stakeholder who strongly supports several unproven technologies for the shopping centre. Concerned about delivery risk and reputation, the project executive asks the project manager to limit the CTO’s contact with the project team and other stakeholders.

Is this an appropriate approach to leading successful change, and why?

Options:

A.

Yes, because restricting the CTO’s involvement would protect the project’s reputation from untested proposals

B.

Yes, because influential stakeholders should be excluded when their preferred solutions create delivery uncertainty

C.

No, because the project manager should record the technological concerns only as risks requiring formal responses

D.

No, because the CTO should remain engaged so that their influence can support adoption across the organizational ecosystem

Buy Now
Question # 13

At the start of stage 3, an approved request for change adds a promotional video to the stage. BuildyBrick has agreed to produce it, a product description has been prepared, and the project manager now needs to instruct the BuildyBrick team manager to begin the work.

During which ‘controlling a stage’ activity should this instruction be given?

Options:

A.

Authorize a work package

B.

Evaluate work package status

C.

Capture issues and risks

D.

Take corrective action

Buy Now
Exam Name: PRINCE2 Project Management Practitioner (Version 7)
Last Update: Oct 3, 2026
Questions: 56
PRINCE2-7-Practitioner pdf

PRINCE2-7-Practitioner PDF

$21.25  $84.99
PRINCE2-7-Practitioner Engine

PRINCE2-7-Practitioner Testing Engine

$23.75  $94.99
PRINCE2-7-Practitioner PDF + Engine

PRINCE2-7-Practitioner PDF + Testing Engine

$33.75  $134.99