Question # 24

What information is NOT typically displayed on a burn chart?

Options:

A.

Effort remaining

B.

Team working agreements

C.

Actual amount of work done

D.

Amount of time elapsed

Buy Now
Question # 25

Which two statements are key responsibilities of supplier representative?

1. They highlight areas that the project may impact from a technical perspective.

2. They are partially assigned to the delivery team.

3. They create the project's specialist products.

4. They prioritize requirements.

Options:

A.

1 and 2

B.

2 and 3

C.

3 and 4

D.

1 and 4

Buy Now
Question # 26

Which is typically used in agile when estimating detailed requirements during sprint planning?

Options:

A.

Rationalism

B.

Trading

C.

Visioning

D.

T-shirt sizing

Buy Now
Question # 27

Which workshop is used to assess the project’s status and address any challenges?

Options:

A.

Team planning workshop

B.

Project retrospective workshop

C.

Team retrospective workshop

D.

Progress review workshop

Buy Now
Question # 28

What is essential to secure leadership buy-in for scaling up agile?

Options:

A.

Speaking the language of leadership

B.

Ensuring that all decisions are made by leadership

C.

Ensuring emphasis on doing agile

D.

Empowering teams to self-manage

Buy Now
Question # 29

Which describes the Scrum Master role in Scrum?

Options:

A.

It is authorized to run the project on a day-to-day basis on behalf of the project board

B.

It is responsible for ensuring that product backlog items are clearly expressed on the product backlog

C.

It is empowered to organize and manage its own work to create a valuable, useful increment every sprint

D.

It is servant-leadership to help everyone change their interactions to maximize the value created by the team

Buy Now
Question # 30

Which process can take place during a release review workshop?

Options:

A.

Controlling a stage

B.

Managing product delivery

C.

Managing a stage boundary

D.

Directing a project

Buy Now
Question # 31

Which TWO are the purposes of a highlight report?

1. To describe the MoSCoW priority of user stories.

2. To summarize the status of a work package.

3. To summarize the stage status.

4. To report any potential issues and risks

Options:

A.

1 and 2

B.

2 and 3

C.

3 and 4

D.

1 and 4

Buy Now
Question # 32

Which statement about the ‘embrace change’ target is CORRECT?

Options:

A.

It minimizes the time needed to train a new team member

B.

It reduces the planning of dependencies between projects

C.

It reduces testing in order to meet deadlines

D.

It encourages the customer to raise new ideas

Buy Now
Question # 33

Which is a purpose of the plans theme?

Options:

A.

To identify any deviations from the project’s objectives

B.

To control any approved changes to the baseline

C.

To monitor actual achievements against those planned

D.

To communicate the approach for delivering products

Buy Now
Exam Name: PRINCE2 Agile Foundation (Version 2) Exam
Last Update: Aug 16, 2025
Questions: 132
PRINCE2-Agile-Foundation pdf

PRINCE2-Agile-Foundation PDF

$25.5  $84.99
PRINCE2-Agile-Foundation Engine

PRINCE2-Agile-Foundation Testing Engine

$28.5  $94.99
PRINCE2-Agile-Foundation PDF + Engine

PRINCE2-Agile-Foundation PDF + Testing Engine

$40.5  $134.99