Weekend Sale 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: Board70

PRINCE2-Agile-Foundation Exam Dumps - PRINCE2 Agile Questions and Answers

Question # 34

When tailoring the plans theme in an agile environment, what is recommended about using a Gantt chart?

Options:

A.

It should be used when planning at the delivery level

B.

It should be used when planning at the project level

C.

It should be used when controlling the quality of the products delivered

D.

It should be used when monitoring the amount of products delivered

Buy Now
Question # 35

Which is an advantage of frequent releases?

Options:

A.

Releases can be used to replace management stages

B.

A ‘one-team’ culture in the project team is encouraged

C.

Configuration management becomes less important

D.

The delivery team becomes more experienced at product handover

Buy Now
Question # 36

Which statement about the ‘accept that the customer doesn’t need everything’ target is correct?

Options:

A.

It gives confidence on the progress of the project

B.

It can result in the early delivery of a minimum viable product

C.

It allows misunderstandings to be dealt with appropriately

D.

It is achieved by managing the culture of the team carefully

Buy Now
Question # 37

Which TWO project board responsibilities are specifically assigned to the senior user?

1) Demonstrating the achievement of benefits.

2) Specifying the needs of those impacted by the outputs.

3) Balancing business, user and supplier demands.

4) Ensuring that the project delivers value for money.

Options:

A.

1 and 2

B.

2 and 3

C.

3 and 4

D.

1 and 4

Buy Now
Question # 38

Which statement about the ‘keep teams stable’ target is CORRECT?

Options:

A.

It applies primarily to the long term, such as a project or a program

B.

It is the primary reason why the tolerance for cost is set to zero

C.

It prevents compromising the overall quality level of the product

D.

It results in the early delivery of a minimum viable product

Buy Now
Question # 39

Which statement about the ‘accept that the customer doesn't need everything’ target is CORRECT?

Options:

A.

It is achieved by testing only a few features to deliver on time

B.

It is achieved by ensuring that the operational product has complete documentation

C.

It is based on the concept that people generally use a limited number of product features

D.

It enables a more accurate final product to be produced

Buy Now
Question # 40

How should team working agreements be created?

Options:

A.

By the supplier subject matter expert agreeing what should be included

B.

By the customer representative deciding what should be included

C.

By team members agreeing on what should be included

D.

By the project manager deciding what should be included

Buy Now
Question # 41

Which PRINCE2 principle should be followed in order to engage the business, user and supplier stakeholder interests?

Options:

A.

Defined roles and responsibilities

B.

Continued business justification

C.

Learn from experience

D.

Tailor to suit the project

Buy Now
Question # 42

What is a role of personas in the 'business case' practice?

Options:

A.

To group users based on demographic data

B.

To ensure project timelines are met

C.

To identify and articulate specific user benefits

D.

To differentiate between product versions

Buy Now
Exam Name: PRINCE2 Agile Foundation (Version 2) Exam
Last Update: Aug 16, 2025
Questions: 132
PRINCE2-Agile-Foundation pdf

PRINCE2-Agile-Foundation PDF

$25.5  $84.99
PRINCE2-Agile-Foundation Engine

PRINCE2-Agile-Foundation Testing Engine

$28.5  $94.99
PRINCE2-Agile-Foundation PDF + Engine

PRINCE2-Agile-Foundation PDF + Testing Engine

$40.5  $134.99