Question # 54

The work package to produce the 'updated corporate quality procedures' was created during stage 3. Before accepting the work package, the team manager produces the team plan and finds that the expected delivery date is unrealistic. As a result, the project manager agrees an extra two weeks to complete the work package, within the current stage tolerance. The work package is then accepted by the team manager.

Is this an appropriate application of the 'manage product delivery' process, and why?

Options:

A.

Yes, because the team manager should set the time required to complete a work package.

B.

Yes, because the team manager should agree the limits within which the work is to be completed.

C.

No, because the work package, defined by the project manager, should not be changed.

D.

No, because the use of the stage time tolerance should be authorized by the project board.

Buy Now
Question # 55

A concern about possible subsidence damage has been recorded as an issue.

Is this an appropriate application of the issues practice, and why?

Options:

A.

Yes, because the concern must be assessed for impact and urgency

B.

Yes, because the historian is an important stakeholder

C.

No, because the historian is not on the project team

D.

No, because the supplier should pay

Buy Now
Question # 56

DIRECTING A PROJECT

Here are three activities that occur during the ‘directing a project’ process.

Which theme (A-E) do they relate to?

Choose only one theme for each activity. Each theme can be used once, more than once, or not at all.

Options:

Buy Now
Question # 57

The project is nearing the end of stage 2. The Sustainability Manager records a lesson learned in the daily log that could be used on other projects in the portfolio.

Is this an appropriate use of the ‘learn from experience’ principle, and why?

Options:

A.

Yes, because the daily log is used for informal issues and lessons

B.

Yes, because recording the lesson ensures learning on this project

C.

No, because the lesson should be shared beyond the project

D.

No, because the lesson should be marked as “logged”

Buy Now
Question # 58

The project is in stage 3. The BuildyBrick construction teams are unsure about using the required environmentally friendly concrete technique. As the team has not used the technique before, the work could take longer than originally planned. The Regeneration Manager has arranged a visit to another site where the technique is being used.

Which principle is being applied, and why?

Options:

A.

Learn from experience, because a field trip provides an opportunity to learn from others

B.

Learn from experience, because lessons should only be reviewed at project start

C.

Manage by exception, because work package time tolerance may be exceeded

D.

Manage by exception, because the CEO should resolve the concern

Buy Now
Question # 59

The project is now in stage 2. The 'training venue specifications' will not be delivered to schedule and the stage is forecast to exceed its time tolerance. As a result, the project manager has agreed with the team manager that the 'training venue specifications' will be delivered in stage 3 instead of stage 2.

Is this an appropriate action, and why?

Options:

A.

Yes, because the project manager should recommend corrective actions required.

B.

Yes, because moving the work enables stage 2 to be delivered within tolerance.

C.

No, because the team manager should inform the project manager by raising an issue.

D.

No, because the stage deviation should be referred to the project board for a decision.

Buy Now
Question # 60

Scenario

A photographer from Portraits Ltd, a professional photographic company, has taken on the role of Team Manager after taking some time to understand the requirements of the project. A contract for their services has been set up and is being monitored by the Purchasing Manager and a Work Package has been agreed. This contract specifies that the photographer must arrange a meeting with the Engineering Manager to establish a schedule for the photo sessions to minimize the impact on the Engineering staff. This meeting should have occurred by now.

The Engineering Manager was made aware of this requirement but when asked he reported that he has received no communication from the photographer. The Project Manager has tried to call the photographer and has had no response. The Project Manager believes there is a risk that Portraits Ltd are overbooking work and prioritizing other clients' work. If Portraits ltd do not deliver on schedule the project will be delayed and the expected benefits will be reduced.

The contract is to be reviewed and Portraits Ltd reminded of their agreement.

The project is now in stage 2. The Project Manager has heard about the possibility of a competitor also producing a calendar to be delivered earlier than the target date for this project. There is a threat that the early release of a competitor's calendar may weaken the impact of the MNO Manufacturing Company calendar, thereby reducing the anticipated benefits of the Calendar project.

Using the Project Scenario answer the following question. The Plan for stage 3 has been approved and work has commenced.

Column 1 contains a number of issues for this project. Select from Column 2 the appropriate category for each issue. Each selection from Column 2 can be used once, more than once or not at all.

Drop down the right answer from column 1 to column 2.

Options:

Buy Now
Question # 61

The project is using PRINCE2's recommended risk management procedure. In the 'identify' step, a risk was recorded in the risk register: ''If the 'accredited classroom-based course' is delayed, there is a threat that work on the 'e-learning course' will be delayed, resulting in the 'accredited e-learning course' not being ready for the 'pilot courses'.''

In the 'implement' step, a risk response was decided: ''Work will start incrementally on the 'e-learning course' whenever a part of the 'classroom-based training materials' gains accreditation''.

Is this appropriate, and why?

Options:

A.

Yes, because delivering incrementally will reduce the impact of the threat.

B.

Yes, because a risk response needs to be implemented for this major threat.

C.

No, because risks responses should be identified as part of the 'plan' step.

D.

No, because a risk action should be allocated to implement a response.

Buy Now
Question # 62

Which of the following statements is False regarding the Risk Management Strategy?

Options:

A.

It captures and maintains all relevant information on identified threats and opportunities

B.

It documents the risk tolerances

C.

It documents the approach to risk

D.

It identifies responsibilities towards risk for the project

Buy Now
Question # 63

Which of the following reports does not contain any information on risk?

Options:

A.

Issue Report

B.

Highlight report

C.

Lessons Report

D.

End Stage Report

Buy Now
Exam Name: PRINCE2 7 Practitioner (7th Edition) Exam
Last Update: Jan 8, 2026
Questions: 263
Prince2-Practitioner pdf

Prince2-Practitioner PDF

$25.5  $84.99
Prince2-Practitioner Engine

Prince2-Practitioner Testing Engine

$28.5  $94.99
Prince2-Practitioner PDF + Engine

Prince2-Practitioner PDF + Testing Engine

$40.5  $134.99