Which of the following is not true regarding applying a model-based approach, e.g., TMMi, for improvements at project level?
You are a test manager managing a test team and working at a government agency. The test team is responsible for performing the system test. Senior management has been provided with the following test objective for a new project:
“The system should be of high quality.”
Using the SMART goal methodology, which of the following statements would be appropriate as a revision to the defined test objective by management?
You are a test manager developing a master test plan. As part of the master test plan, you are defining exit criteria for the various test levels.
Which of the following exit criteria would be most appropriate and SMART for component testing, and which one would be most appropriate and SMART for system testing?
i. 95% of the tests prepared are executed successfully
ii. All test cases have been run
iii. 80% decision coverage for all tests run
iv. At least 30 defects have been found
v. At least two weeks of test execution
vi. No more open defects
For which type of testing would a test manager be involved with establishing benchmarks?
You are currently leading an independent test team. Based on the information given in the scenario, identify how the team could be improved most effectively.