Question # 4

An architect is responsible for the availability design of a solution.

The following information has been provided:

Virtual machines (VMs) run 8 or less vCPUs

All hosts have a minimum of two NICs per vSphere distributed switch (VDS) connected to separate physical switches

All hosts have a minimum of two host bus adapters (HBAs) connected to separate physical switches

Which three options maximize VM availability in the event of an ESXi host failure? (Choose three.)

Options:

A.

vSphere High Availability Restart Priority set to default at the cluster level

B.

vSphere NIC Teaming policy: Route based on originating port ID set on the distributed port group

C.

vSphere Fault Tolerance configured on the virtual machines

D.

vSphere Round Robin storage multi-pathing policy set on each ESXi host

E.

VMware Tools configured to automatically update on reboot for all virtual machines

F.

Dynamic Link Aggregation (LACP) configured on the distributed virtual switch

Buy Now
Question # 5

An architect is responsible for extending the hosting design for a customer. The customer has a mission-critical 3-node application which is load balanced in an active/active/passive configuration. The application administrator requests that the virtual infrastructure team be responsible for maintaining platform level availability. An organizational policy exists to mandate the highest possible availability for mission-critical applications.

Based on the resource requirements, the architect has made the following design decision:

The target vSphere cluster contains three VMware ESXi host servers

A combination of which additional four physical design decisions should the architect make to maximize availability of the application? (Choose four.)

Options:

A.

The solution will create a VM-Host Affinity rule that specifies that workloads must run on hosts in a group.

B.

The solution will enable vSphere High Availability (HA) with restart priority set to "Highest" for the application virtual machines.

C.

The solution will create a VM-VM Affinity rule to keep virtual machines separate.

D.

The solution will create a host DRS group containing all hosts within the cluster.

E.

The solution will enable vSphere Fault Tolerance with vSphere High Availability (HA) virtual machine component failure enabled.

F.

The solution will create a virtual machine DRS group that contains all of the critical application workloads.

G.

The solution will create a VM-VM Affinity rule to keep virtual machines together.

Buy Now
Question # 6

An architect is documenting the design for a new multi-site vSphere solution. The customer has informed the architect that the workloads hosted on the solution are managed by application teams, who must perform a number of steps to return the application to service following a failover of the workloads to the secondary site. These steps are defined as the Work Recovery Time (WRT). The customer has provided the architect with the following information about the workloads:

Critical workloads have a WRT of 12 hours

Production workloads have a WRT of 24 hours

Development workloads have a WRT of 24 hours

All workloads have an RPO of 4 hours

Critical workloads have an RTO of 1 hour

Production workloads have an RTO of 12 hours

Development workloads have an RTO of 24 hours

The customer has also confirmed that the Disaster Recovery solution will not begin the recovery of the development workloads until all critical and production workloads have been recovered at the secondary site.

What would the architect document as the maximum tolerable downtime (MTD) for each type of workload in the design?

Options:

A.

Critical Workloads: 13 hoursProduction Workloads: 36 hoursDevelopment Workloads: 48 hours

B.

Critical Workloads: 13 hoursProduction Workloads: 36 hoursDevelopment Workloads: 60 hours

C.

Critical Workloads: 12 hoursProduction Workloads: 24 hoursDevelopment Workloads: 24 hours

D.

Critical Workloads: 16 hoursProduction Workloads: 28 hoursDevelopment Workloads: 28 hours

Buy Now
Question # 7

An architect is designing a backup solution.

Which two statements should be included in the logical design for this solution? (Choose two.)

Options:

A.

The database must be backed up even/ day during the maintenance window of 1:00AM and 3:00AM.

B.

The network that will be used for backups will be configured to use VLAN ID 1511.

C.

The bkp-nfs-01 datastore will be used for backups.

D.

The company's existing backup solution will be unsupported by the third-party vendor in six months.

E.

The database will be backed up using an API-based backup solution.

Buy Now
Question # 8

An architect is holding a design workshop with a customer for a new solution. The customer states that the new solution needs to provide the following capabilities:

Automated deployment and lifecycle management of the vSphere platform

Self-Service deployment of virtual machines and other objects from a central catalog

Monitoring, logging and analytic tooling to provide visibility and troubleshooting of the whole solution

Support deployment via infrastructure-as-code methods for the additional management components

The customer also requests that the solution be as cost-effective as possible while still delivering a fast time to value for the organization.

Which design approach should the architect recommend to meet these requirements?

Options:

A.

Use VMware Validated Designs for the vSphere solution and VMware Validated Solutions for the additional components

B.

Use VMware Cloud Foundation for the vSphere solution and VMware Validated Solutions for the additional components

C.

Use VMware Cloud Foundation for the vSphere solution and a custom design for the additional components

D.

Use a custom design for the vSphere solution and VMware Validated Solutions for the additional components

Buy Now
Question # 9

A company will be replacing the external storage array that is currently providing storage to the vSphere environment. The architect must design a storage architecture for existing and future workloads. Company policy required storage separation of workloads by departments.

Which design decision should the architect make to satisfy the requirement and scale for additional departments?

Options:

A.

Use storage volumes based on applications.

B.

Use one storage volume per department and create new volumes for new departments.

C.

Use one storage volume per existing department and extend current volumes for new departments.

D.

Use N + 1 storage volumes for current and future workloads.

Buy Now
Question # 10

An architect is designing a new vSphere solution. The following information has been gathered during the design workshops with the customer:

The solution will be deployed into two availability zones (AZs)

The solution will be configured as a single stretched cluster with shared storage across the two AZs

Production and Development workloads will run across both AZs

The cluster is configured as N + 1

The architect needs to ensure that, in the event of a host failure during maintenance of another host in the cluster, only the Production workloads are recovered.

What should the architect include in the design to meet this requirement?

Options:

A.

Configure vSphere HA VM Monitoring to VM and Application MonitoringSet the VM monitoring sensitivity to Custom

B.

Configure vSphere HA VM Monitoring to VM Monitoring onlySet the VM monitoring sensitivity to Preset of High

C.

Configure vSphere HA Host Failure Response to Restart VMsSet the Development VMs to Disabled as the Restart Priority

D.

Configure vSphere HA Host Failure Response to Restart VMsSet the cluster default Restart VM Restart Priority to Highest

Buy Now
Question # 11

An architect is creating a design for a new vSphere solution to meet the following business requirement:

REQ001 - Reduce operational expenditure

Which design decision could the architect include in the logical design to satisfy this requirement?

Options:

A.

Use vSphere Standard licenses on all clusters.

B.

Use heterogeneous hardware for the hosts in all clusters.

C.

Use vSphere Lifecycle Manager on all clusters.

D.

Use an N + 1 design to define the required capacity on all clusters.

Buy Now
Question # 12

An architect is designing a new vSphere-based solution for a customer.

During a requirements gathering workshop, the following information is provided:

The solutions must provide a recovery point objective (RPO) of 15 minutes.

The solution must have a primary and secondary site.

The solution must support orchestration to address application dependencies.

Which two solutions should the architect include in the design to meet these requirements? (Choose two.)

Options:

A.

vSAN stretched cluster

B.

vSphere HA

C.

Site Recovery Manager

D.

vSphere Fault Tolerance

E.

vSphere Replication

Buy Now
Question # 13

An architect is responsible for the lifecycle management design for a brownfield vSphere-based solution.

The following information has been provided during initial meetings around the new solution:

Existing heterogeneous server hardware will be used to provide the hosting platform.

The available hardware is:

-- 10 servers that contain 2 x 20-Core Intel Xeon processors and 512 GB RAM from Vendor A

-- 10 servers that contain 2 x 24-Core Intel Xeon processors and 768 GB RAM from Vendor A

-- 20 servers that contain 2 x 16-Core AMD EPYC processors and 512 GB RAM from Vendor B

-- 10 servers that contain 1 x 24-Core AMD EPYC processors and 256 GB RAM from Vendor C

All of the hardware is currently listed on the VMware Hardware Compatibility List (HCL).

All existing server hardware has 36 months vendor support remaining.

The requirements from the customer are:

REQ001 - The solution must support the hosting of 5,000 workloads across two physical sites.

REQ002 - The solution should minimize the number of clusters.

REQ003 - The solution must ensure that there is no impact to service when completing upgrades.

Given the resource requirements needed for the solution, the architect has calculated that all of the existing servers will be required to provide sufficient resources for the new environment. The Intel-based servers will be deployed to the primary site and the AMD-based servers will be

deployed to the secondary site.

Which four additional design decisions should the architect make to ensure all requirements can be met? (Choose four.)

Options:

A.

The solution will create an Intel-based 20-node vSphere cluster in the primary site and an AMD-based 30-node vSphere cluster in the secondary site.

B.

The solution will use VMware SDDC Manager to perform lifecycle management of the solution.

C.

The solution will ensure each vSphere cluster supports a minimum of N + 1 redundancy.

D.

The solution will use vSphere Lifecycle Manager images to update and upgrade vSphere ESXi hosts in the secondary site.

E.

The solution will use vSphere Lifecycle Manager baselines to perform patching and upgrading of vSphere ESXi hosts in the secondary site.

F.

The solution will use vSphere Lifecycle Manager images to update and upgrade vSphere ESXi hosts in the primary site.

G.

The solution will ensure each vSphere cluster is configured with Distributed Power Management (DPM).

Buy Now
Exam Code: 3V0-21.23
Exam Name: VMware vSphere 8.x Advanced Design
Last Update: Aug 1, 2025
Questions: 92
3V0-21.23 pdf

3V0-21.23 PDF

$25.5  $84.99
3V0-21.23 Engine

3V0-21.23 Testing Engine

$28.5  $94.99
3V0-21.23 PDF + Engine

3V0-21.23 PDF + Testing Engine

$40.5  $134.99