Summer Sale 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: Board70

BIM_MGT_101 Exam Dumps - Autodesk Certified Professional Questions and Answers

Question # 14

During an initial coordination meeting, the team agreed that the contractor will be able to mark up the latest model and sheets in Autodesk Forma every week.

Which two actions should the BIM Manager take to ensure this is implemented correctly? (Select two.)

Options:

A.

Email PDFs to the contractor every week.

B.

Update Publish Settings to include sheets.

C.

Create blank sheets for all disciplines.

D.

Enable Model Coordination.

E.

Schedule Publishes in Design Collaboration.

Buy Now
Question # 15

A BIM manager is creating a firm-wide template for mobilization plans to outline the key steps, resources, and strategies required to set up and launch BIM operations at the beginning of projects.

Which two components should the template include to accomplish the goal? (Select two.)

Options:

A.

Common Data Environment.

B.

Contract template.

C.

Roles and responsibilities.

D.

Specifications.

E.

Project milestone dates.

Buy Now
Question # 16

A design team requests a focused coordination review between the Architectural and Structural published design models. They want to exclude all other trades from the clash matrix.

What should the BIM manager do to ensure only the Architectural and Structural models are included in clash detection?

Options:

A.

Request each non-relevant discipline to temporarily remove its views from the coordination environment.

B.

Merge all models into a single federated model and manually hide non-relevant elements.

C.

Run clash detection on all models but only review the issues between Architectural and Structural.

D.

Assign only the Architectural and Structural models to a dedicated coordination group before running clash detection.

Buy Now
Question # 17

A team member accidentally unpinned and dragged a linked CAD file, and it is no longer aligned according to the Shared Coordinates.

How can the BIM manager realign the linked CAD file in the Revit model?

Options:

A.

Publish the Coordinates from the host model to the linked CAD file.

B.

Select the linked CAD file and use the Move command to realign the link.

C.

Select the Shared Site of the linked CAD file and move the instance to the defined Site.

D.

Ask the consultant to update the CAD file and relink it.

Buy Now
Question # 18

The BIM manager is launching a civic center project with strict sustainability and lifecycle data goals. During early planning, each discipline proposes different modelling approaches, and there is concern that downstream data handoff may be inconsistent.

To establish BIM goals and uses that ensure alignment from design through operations, what should the BIM manager do first?

Note: In the context of this exam, the term Level of Development (LOD) is used interchangeably with level of information need.

Options:

A.

Ask each team to submit its standard BEPs for review and consolidate them into one reference document.

B.

Finalize the LOD matrix and data drops based on similar past projects, updating it during the design process as needed.

C.

Begin developing the internal BIM templates and content, assuming they will be applicable to this project.

D.

Host a stakeholder session to review the project-specific requirements and BIM uses, and establish mobilization needs and modelling requirements.

Buy Now
Question # 19

A government facility project requires unique data formatting and export requirements that comply with a global data-management initiative. A workflow utilizing a newly released add-on tool is developed to perform this task.

How should a BIM manager define training and ensure the appropriate staff receive it?

Options:

A.

Create training tutorials for the unique tasks and assign them to the members whose roles are responsible for the tasks.

B.

Develop a full training curriculum and assign all members of the project team, regardless of role.

C.

Assign the task to the team and provide training to any user whose Journal reveals a crash.

D.

Review each project model at milestone deliveries and assign the team training on items that fail the quality-control review.

Buy Now
Question # 20

The BIM manager received a subcontractor’s 3D model containing specialty equipment to be integrated into the federated model. Upon review, they observe that:

    Many elements lack consistent object styles and category assignments.

    Some components are modelled with excessive detail, affecting performance.

    Embedded data does not follow the project’s naming conventions outlined in the BEP.

What is the most appropriate next step when evaluating this geometry and content?

Options:

A.

Instruct the subcontractor to simplify geometry and reduce file size, even if some metadata and classifications are lost.

B.

Approve the model as-is to avoid delaying coordination and document the issues for review at the next quality-control milestone.

C.

Review the model against content standards, document noncompliance, and request revisions aligned with agreed deliverable requirements.

D.

Import the model into the coordination environment and apply view filters to hide excessive detail and inconsistencies.

Buy Now
Exam Code: BIM_MGT_101
Exam Name: Autodesk Certified Professional in BIM Management for Building Design
Last Update: Aug 26, 2026
Questions: 57
BIM_MGT_101 pdf

BIM_MGT_101 PDF

$25.5  $84.99
BIM_MGT_101 Engine

BIM_MGT_101 Testing Engine

$28.5  $94.99
BIM_MGT_101 PDF + Engine

BIM_MGT_101 PDF + Testing Engine

$40.5  $134.99