Labour Day Special Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: bigdisc65

All PK0-004 Test Inside CompTIA Questions

Page: 2 / 29
Question 8

During an ad-hoc meeting, the OM notifies the sponsor that while the project is on schedule, material costs have increased and the project is over budget. To save the project, the PM request a material contract with a less expensive vendor. The sponsor approves the change, and project comes in within target tolerances. The company, however, receives numerous stakeholder complaints.

Which of the following is the MOST likely cause of these complaints?

Options:

A.

The quality of the deliverable decreased due to the rising material cost.

B.

The PM did not follow the project communication plan.

C.

Quality assurance actions were not adjusted for the vendor change.

D.

The change was not documented and approved.

Question 9

Which of the following defines the minimum level of engagement of a stakeholder?

Options:

A.

Passive

B.

Invested

C.

Contributing

D.

Interested

Question 10

Given the information in the table below, which of the following is the total project cost?

Options:

A.

$40,000

B.

$70,000

C.

$95,000

D.

$120,000

Question 11

A Chief Executive Officer (CEO) has approached a project team member to request a project change.

Which of the following would be the BEST step for the project manager to take to prevent scope creep?

Options:

A.

Deny the CEO’s request.

B.

Implement the project change.

C.

Submit the request to the CCB.

D.

Ask the CEO to follow the communications plan.

Page: 2 / 29
Exam Code: PK0-004
Exam Name: CompTIA Project+ Exam
Last Update: Apr 24, 2024
Questions: 796
PK0-004 pdf

PK0-004 PDF

$28  $80
PK0-004 Engine

PK0-004 Testing Engine

$33.25  $95
PK0-004 PDF + Engine

PK0-004 PDF + Testing Engine

$45.5  $130