Labour Day Special Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: bigdisc65

CPIM-Part-2 Exam Results

Page: 3 / 11
Question 12

Compared to traditional supplier relationships, a more strategic view of supplier relationships would require:

Options:

A.

maintaining communication based on trust.

B.

offering the supplier more business.

C.

adopting electronic data interchange (EDI).

D.

implementing concurrent engineering.

Question 13

Establishment of goals and baselines prior to entering the plan-do-check-act (FDCA) cycle allows improvement teams to:

Options:

A.

determine whether an effective change was made in the process.

B.

determine if improvement potential is complete.

C.

assure successful completion of the improvement effort.

D.

complete the project with fewer iterations.

Question 14

Potential reasons to make instead of buy a product may include:

Options:

A.

maintain core competencies, increase capital expense, and reduce cost.

B.

less capital investment, large volume changes, and reduce cost.

C.

maintain quality, reduce cost, and keep confidential processes within the firm.

D.

eliminate risks associated with single sourcing, create intermittent flow, and reduce cost.

Question 15

What is a result of effective production activity control (PAC)?

Options:

A.

Actual input/output matches planned input/output

B.

Less scrap and rework on the shop floor

C.

Fewer machine hours are required for production

D.

Available capacity is increased ®

Page: 3 / 11
Exam Code: CPIM-Part-2
Exam Name: Certified in Planning and Inventory Management(Part 2)
Last Update: May 8, 2024
Questions: 151
CPIM-Part-2 pdf

CPIM-Part-2 PDF

$28  $80
CPIM-Part-2 Engine

CPIM-Part-2 Testing Engine

$33.25  $95
CPIM-Part-2 PDF + Engine

CPIM-Part-2 PDF + Testing Engine

$45.5  $130