Labour Day Special Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: bigdisc65

PK0-005 Premium Exam Questions

Page: 3 / 17
Question 12

Which of the following should be the PRIMARY basis for establishing metrics that measure the effectiveness of an information security program?

Options:

A.

Residual risk

B.

Regulatory requirements

C.

Risk tolerance

D.

Control objectives

Question 13

Two developers are discussing the design solution for a particular feature. The meeting is taking longer than expected, and the parties have been unable to reach an agreement. The project manager decides to take a break and continue the meeting on another day. Which of the following techniques is the project manager using?

Options:

A.

Avoiding

B.

Smoothing

C.

Forcing

D.

Compromising

Question 14

A project manager has been assigned to a new project. During the planning phase, the project manager needs to get an understanding of the purpose of the project. Which of the following should the project manager do?

Options:

A.

Collate the lessons learned.

B.

Perform a gap analysis.

C.

Review existing artifacts.

D.

Conduct a retrospective.

Question 15

A project team is defining operational training, discussing a go-live date, and describing the operational handoff. Which of the following best describes what the team is developing?

Options:

A.

The project closeout report

B.

A handover to operations

C.

Phase-gate review documentation

D.

A transition plan

Page: 3 / 17
Exam Code: PK0-005
Exam Name: CompTIA Project+ Certification Exam
Last Update: Apr 24, 2024
Questions: 239
PK0-005 pdf

PK0-005 PDF

$28  $80
PK0-005 Engine

PK0-005 Testing Engine

$33.25  $95
PK0-005 PDF + Engine

PK0-005 PDF + Testing Engine

$45.5  $130