Spring Sale 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: Board70

PK0-005 Exam Dumps - CompTIA Project+ Questions and Answers

Question # 4

While in the closing phase of a project, the project manager gathers feedback from stakeholders. Which of the following best describes a benefit of this feedback?

Options:

A.

It highlights the performance issues of the project manager and team members.

B.

It lets the project manager know which stakeholders are allies for future projects.

C.

It helps the project manager create a more structured lessons-learned session.

D.

It identifies the stakeholders' real opinions about the project.

Buy Now
Question # 5

When assigning access, classifying information based on sensitivity is referred to as:

Options:

A.

Digital security

B.

Physical security

C.

Data security

D.

Operational security

Buy Now
Question # 6

A project manager needs to ensure that the products produced during the project meet the highest quality standards and that team members understand the importance of these standards. Which of the following should the project manager do?

Options:

A.

Train the team members.

B.

Assess the resource pool.

C.

Develop a QA plan.

D.

Create RACI matrix.

Buy Now
Question # 7

A project manager is starting a new project for an international supplier. Which of the following is the first step the project manager should take to initiate the project?

Options:

A.

Identify project risks and plans to address them.

B.

Identify business needs and product descriptions.

C.

Create a work breakdown structure for the project.

D.

Create a work schedule for the project team to follow.

Buy Now
Question # 8

During the project execution phase, Ann, a project manager, received an email from the project sponsor asking for an additional work package to be added to the project scope due to new legislation.

INSTRUCTIONS

Review the email with the latest updates sent by the project sponsor and respond in

the following order:

1. Select the best tool for tracking the server migration progress.

2. Select the new critical path.

3. Select the correct number of engineers required for the server migration phase.

If at any time you would like to bring back the initial state of the simulation, please click

the Reset All button.

Select the Appropriate Tool:

Select the new critical path.

Option A

Option B

Option C

Options:

Buy Now
Question # 9

Several months after a project has ended, a project team member is still charging time to the project and is unable to charge time to new projects. Which of the following did the project manager neglect to do?

Options:

A.

Remove the team member's access.

B.

Release the project resources.

C.

Collect the stakeholders’ feedback.

D.

Have the closeout report approved.

Buy Now
Question # 10

A global franchise requests that a company provide a solution to unify its operation worldwide. Additionally, the company would like the solution to provide operation reports in real time without asking the country franchise manager for these reports. Which of the following cloud models would the company suggest to the global franchise?

Options:

A.

laaS

B.

XaaS

C.

PaaS

D.

SaaS

Buy Now
Question # 11

As a result of an approved change, the project manager updates the project plan with the newest project end date. Which of the following change control processes should the project manager complete NEXT?

Options:

A.

Document the request in the change control log.

B.

Communicate the change deployment.

C.

Conduct an impact assessment.

D.

Implement the change.

Buy Now
Question # 12

A PM is working with stakeholders in the discovery phase and comparing the cost of the project to the cost savings the project will produce when it is complete. The output of this exercise will produce the:

Options:

A.

ROI.

B.

SOW.

C.

RFI.

D.

RPR

Buy Now
Question # 13

After releasing an application into production, a major defect is detected. The project team implements a work-around that fixes the issue for now. Which of the following should the team do next?

Options:

A.

Provide the change to the CCB.

B.

Perform root cause analysis.

C.

Escalate to the project steering committee.

D.

Update the risk register.

Buy Now
Exam Code: PK0-005
Exam Name: CompTIA Project+ Certification (2026)
Last Update: Apr 5, 2026
Questions: 447
PK0-005 pdf

PK0-005 PDF

$25.5  $84.99
PK0-005 Engine

PK0-005 Testing Engine

$28.5  $94.99
PK0-005 PDF + Engine

PK0-005 PDF + Testing Engine

$40.5  $134.99