Question 24

A system was implemented, and testing was successfully completed. Which of the following should the project manager do NEXT?

Options:

A.

Validate against the scope statement and ask for sign-off.

B.

Run a control chart to ensure the quality of the deliverables.

C.

Review the risk register and close up residual risks.

D.

Start the training and handoff for the operations team.

Question 25

Following the approval of a change by the CCB, which of the following should a project manager consider next when deploying a new networking device into an existing production environment?

Options:

A.

Maintenance window

B.

Risk assessment

C.

Operational security

D.

Validation check

Question 26

A project manager needs to update the project sponsor and senior stakeholders about the progress of a project. Which of the following tools will the project manager MOST likely use?

Options:

A.

Dashboard

B.

Gantt chart

C.

Work breakdown structure

D.

Requirements Traceability Matrix

Question 27

A financial manager reports that several employees' allocations from the past month appear to be 200% even though they are only assigned to a particular project. Which of the following could MOST likely be the cause of this issue?

Options:

A.

A project manager assigned the wrong resources.

B.

A project manager did not release the resources

C.

A project manager did not remove the system access.

D.

A project manager did not provide the project sign-off.

Page: 6 / 17
Exam Code: PK0-005
Exam Name: CompTIA Project+ Certification Exam
Last Update: Apr 30, 2024
Questions: 239
PK0-005 pdf

PK0-005 PDF

$28  $80
PK0-005 Engine

PK0-005 Testing Engine

$33.25  $95
PK0-005 PDF + Engine

PK0-005 PDF + Testing Engine

$45.5  $130