Summer Limited Time 60% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: dealsixty

Vce PK0-004 Questions Latest

Page: 13 / 29
Question 52

Which of the following are characteristics of a project? (Choose two.)

Options:

A.

Ongoing

B.

Temporary

C.

Start and finish

D.

Achieving a goal

E.

Consisting of milestones

F.

Restricting the budget

Question 53

The project manager is reviewing the earned value of work completed compared to the planned value and is representing it in a dollar figure.

This type of analysis is an example of which of the following?

Options:

A.

Cost performance index

B.

Risk mitigation

C.

Schedule variance

D.

Cost variance

Question 54

The client accepts the critical design review.

Which of the following meetings should be held to move to the NEXT step in the project?

Options:

A.

Execution

B.

Kickoff

C.

Closure

D.

Planning

Question 55

A project manager was directed to complete a project sooner than previously planned. Which of the following is the MOST cost-effective step to take to ensure the project’s success?

Options:

A.

Reduce the scope

B.

Increase the budget

C.

Decrease staff

D.

Update the WBS

Page: 13 / 29
Exam Code: PK0-004
Exam Name: CompTIA Project+ Exam
Last Update: Apr 18, 2024
Questions: 796
PK0-004 pdf

PK0-004 PDF

$32  $80
PK0-004 Engine

PK0-004 Testing Engine

$38  $95
PK0-004 PDF + Engine

PK0-004 PDF + Testing Engine

$52  $130