Spring Sale 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: Board70

MSP-Practitioner Exam Dumps - PeopleCert MSP Questions and Answers

Question # 14

The project manager for the Customer Processes Project has heard a rumour that Web ‘n’ Go is having financial difficulties. If this company becomes bankrupt, they will not be able to supply the agreed customer web-based portal services which are required to enable the single customer services call centre. The programme manager has added this risk to the programme risk register.

Is this action by the programme manager an appropriate application of the ‘design’ theme, and why?

Options:

A.

Yes, because the web-based portal services are needed to reduce staff levels and associated costs

B.

Yes, because projects should escalate risks that could affect the project's objectives to the programme manager

C.

No, because the vision and target operating model should be developed as part of the ‘design’ theme

D.

No, because this is just a rumour and no action is needed until Web ‘n’ Go is actually bankrupt

Buy Now
Question # 15

One of the outcomes from the programme is 'customers buy package deals'. However, this outcome cannot be fully achieved until the end of Tranche 3 when training for the call centre staff is complete. Some senior managers think that this could be delivered more quickly, but the Call Centre Manager does not want their staff members affected by too many changes at the same time, so that they can continue to meet the needs of existing customers. The programme manager has designed the tranche structure to take this into account.

Is this tranche design an appropriate application of the 'bring pace and value' principle, and why?

Options:

A.

Yes, because the timing of delivery must consider the needs of normal business-as-usual activities

B.

Yes, because the programme manager should be empowered to design the delivery plan to meet the business needs

C.

No, because the BCM should be responsible for deciding when the transition to new ways of working should start

D.

No, because the priority of the programme is to deliver the vision and benefits as early as possible

Buy Now
Question # 16

Which of the following is kind of a vision led programme?

Options:

A.

Programme evolved from concurrent, individual projects with need to ensure compliance to organization strategy

B.

Must do programmes due to change in legislation

C.

Public programme started to fulfil electoral promises

D.

Programme focused on bringing organization in tune with laws of the country of operations

Buy Now
Question # 17

Which of following is correct about Benefits Management?

Options:

A.

Ensures programme does right things and is aligned with strategy

B.

Ensures programme is aware of positive and negative impact it might generate

C.

Is tightly aligned to transformational flow processes

D.

All of above

Buy Now
Question # 18

Which principle ensures creating a 'Vision'?

Options:

A.

Adding value

B.

Leading Change

C.

Envisioning and communicating a better future

D.

Focusing on benefits and threats to them

Buy Now
Question # 19

Which of below sentences describes Project Brief?

Options:

A.

List of all projects that will be part of programme

B.

Control framework for programme

C.

Control framework for projects

D.

Describes purpose, cost, time, performance requirements and constraints of a project

Buy Now
Question # 20

The programme is now in the ‘close the programme’ process. All the planned training from the Training Project has been completed. However, it is too early to tell how much impact the training will have on service to customers. This will need to be monitored during normal business operation.

Which theme is MOST relevant to this situation?

Options:

A.

Design

B.

Knowledge

C.

Organization

D.

Structure

Buy Now
Question # 21

The programme is in Tranche 2 and has been progressing according to plan. However, there have been difficulties transitioning to the new ways of working at the end of Tranche 1 and UU has had some customer complaints as a result. Therefore, the SRO asked the programme manager to replan the programme so that all remaining capabilities are transitioned at the end of the programme, instead of at the end of the tranche.

Is this an appropriate application of the 'structure' theme, and why?

Options:

A.

Yes, because applying the ‘lead with purpose’ principle requires delivery to be planned to realize outcomes of benefit

B.

Yes, because applying the 'collaborate across boundaries' principle requires effective use of programme resources

C.

No, because applying the ‘realize measurable benefits’ principle requires outcomes of benefit to be embedded at intermediate landing points

D.

No, because applying the ‘align with priorities' principle requires the content of the tranches to be changed, rather than delaying transition

Buy Now
Question # 22

Which of following is not expected from senior leadership of programme?

Options:

A.

Skilful in active management of cultural and people issues

B.

Ability to create a compelling vision portraying a beneficial future

C.

Empowered decision making

D.

Good budgeting and resource allocation skills

Buy Now
Question # 23

Which of the following is an Information Baseline?

Options:

A.

Governance

B.

Boundary

C.

Management

D.

All of above

Buy Now
Exam Code: MSP-Practitioner
Exam Name: MSP Practitioner, 5th edition Exam
Last Update: Feb 20, 2026
Questions: 133
MSP-Practitioner pdf

MSP-Practitioner PDF

$25.5  $84.99
MSP-Practitioner Engine

MSP-Practitioner Testing Engine

$28.5  $94.99
MSP-Practitioner PDF + Engine

MSP-Practitioner PDF + Testing Engine

$40.5  $134.99