PK0-005 Exam Dumps - CompTIA Project+ Questions and Answers

Question # 94

An IT intern was assigned to set up workstations as part of a project. The IT intern was very careful to do the task well and initially referred to notes while performing the task. By the end of the two-week rotation, the IT intern no longer needed the notes and completed more set-ups in less time. Which of the following MOST likely represents the observed relationship in this scenario?

A)

B)

C)

D)

Options:

A.

Option A

B.

Option B

C.

Option C

D.

Option D

Buy Now
Question # 95

A sponsor prefers to communicate with the team using email, phone calls, conversations in the hallway, and impromptu meetings. Which of the following types of communication is the sponsor using?

Options:

A.

Informal communication

B.

Formal communication

C.

Synchronous communication

D.

Asynchronous communication

Buy Now
Question # 96

A project manager is eager to define access requirements during the initiation phase of a project. Which of the following steps should the project manager perform first?

Options:

A.

Define the WBS.

B.

Develop a RAM.

C.

Manage the vendors.

D.

Assess the resource pool.

Buy Now
Question # 97

A project stakeholder has asked the project manager to provide the performance data of a project. Which of the following should the project manager send to the stakeholder?

Options:

A.

Issue log

B.

Dashboard

C.

WBS

D.

Milestone chart

Buy Now
Question # 98

An institution wants to implement software solutions to help manage the internal flow for formally responding in writing to citizens' complaints. Which of the following solutions would be BEST?

Options:

A.

Enterprise resource planning and end user applications

B.

Electronic document and record management systems

C.

Customer relationship management and databases

D.

Content management and financial systems

Buy Now
Question # 99

To gather requirements from stakeholders, the project manager sits down with them and allows them to discuss freely. Which a following technique is the project manager utilizing?

Options:

A.

Process moving

B.

Brainstorming

C.

Interview

D.

Focus group

Buy Now
Question # 100

A developer recommends modifying an existing portion of code that is not part of the scope and is causing low performance on the current solution. Which of the following actions should the project manager most likely take?

Options:

A.

Ask a developer to create a change request.

B.

Do nothing because recommendation is scope creep.

C.

Ask a developer to implement the recommendation.

D.

Communicate the change status.

Buy Now
Question # 101

A project scheduler updates the project status with the following information: SPI = 1.25 and CPI = 0.85. Which of the following can the project manager infer about the current project status?

Options:

A.

The project is ahead of schedule and under budget.

B.

The project is behind schedule and over budget

C.

The project is ahead of schedule and over budget.

D.

The project is behind schedule and under budget

Buy Now
Question # 102

During a status meeting, the development team reviews work and finds an unforeseen dependency on one of the critical project activities. As a result, the project will most likely be delayed. Which of the following actions should the project manager MOST likely perform?

Options:

A.

Work with the project scheduler to update the project timeline.

B.

Communicate to the stakeholders about the updated timeline.

C.

Ask the development team to fast-track upcoming activities.

D.

Add two resources so the critical activities will finish on time.

Buy Now
Question # 103

As a part of a project, structured cabling activities have been outsourced to another company. The agreement is that work will take six weeks to complete and will be performed at different locations. Which of the following should the project manager do? (Select two).

Options:

A.

Purchase the materials.

B.

Assign the resources.

C.

Accept delays in the work.

D.

Approve the deliverables.

E.

Monitor the performance.

F.

Negotiate with the vendors.

Buy Now
Exam Code: PK0-005
Exam Name: CompTIA Project+ Certification (2026)
Last Update: Mar 11, 2026
Questions: 447