Weekend Special Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: bigdisc65

PK0-005 Exam Dumps - CompTIA Project+ Questions and Answers

Question # 94

A data center is under construction, and the project manager wants to address the risks related to physical injuries. Which of the following is the best risk response method for this scenario?

Options:

A.

Avoid injuries by using robots to perform tasks.

B.

Transfer risk to an insurance company.

C.

Mitigate risk by training the construction workers.

D.

Accept the risks inherent to construction.

Buy Now
Question # 95

A project manager sent equipment to a global project team for testing purposes. Only 70% of the project team received the equipment for testing. Which of the following considerations is impacting the rest of the team?

Options:

A.

Quality assurance

B.

Organizational branding restrictions

C.

State privacy acts

D.

Country legal regulations

Buy Now
Question # 96

A sponsor is working on a document that states the objectives and success criteria of the project, as well as the person to be appointed as project manager Which of the following should the newly appointed project manager do next?

Options:

A.

Conduct a risk assessment.

B.

Create a project scope document

C.

Identify stakeholders

D.

Perform a lessons learned.

Buy Now
Question # 97

A project manager is reviewing quality planning techniques. Which of the following involves comparing results of similar activities?

Options:

A.

Performing a cost-benefit analysis

B.

Defining metrics

C.

Benchmarking

D.

Brainstorming

Buy Now
Question # 98

During a status meeting, the development team reviews work and finds an unforeseen dependency on one of the critical project activities. As a result, the project will most likely be delayed. Which of the following actions should the project manager MOST likely perform?

Options:

A.

Work with the project scheduler to update the project timeline.

B.

Communicate to the stakeholders about the updated timeline.

C.

Ask the development team to fast-track upcoming activities.

D.

Add two resources so the critical activities will finish on time.

Buy Now
Question # 99

A project manager has decided to outsource portions of a project and will conduct a separate procurement. In which of the following phases does this task occur?

Options:

A.

Planning

B.

Initiating

C.

Controlling

D.

Executing

Buy Now
Question # 100

Which of the following is a characteristic that defines a project?

Options:

A.

Will produce a profit

B.

Uses outside resources

C.

Requires a well-defined scope

D.

Has a defined start and finish

Buy Now
Question # 101

During the testing phase of a project, the regression test fails due to a specific item that is disrupting the entire system. Which of the following documents should the project manager use to identify who requested this item?

Options:

A.

Issue log

B.

Risk register

C.

Defect log

D.

Traceability matrix

Buy Now
Question # 102

During the testing phase of a project, an executive raises a concern about a missing requirement in the product. Which of the following is the next step the project manager should take?

Options:

A.

Communicate the change status.

B.

Ask for a change request submission

C.

Escalate to the change control board

D.

Reject the change to prevent scope creep.

Buy Now
Question # 103

A system is scheduled to go live, and the client signed an SLA. Which of the following elements is part of the agreement?

Options:

A.

Resolution time

B.

Issue list

C.

Work breakdown structure

D.

Cost optimization

Buy Now
Exam Code: PK0-005
Exam Name: CompTIA Project+ Certification (2025)
Last Update: Oct 2, 2025
Questions: 386
PK0-005 pdf

PK0-005 PDF

$29.75  $84.99
PK0-005 Engine

PK0-005 Testing Engine

$33.25  $94.99
PK0-005 PDF + Engine

PK0-005 PDF + Testing Engine

$47.25  $134.99