Question # 94

While developing a project charter, a PM discovers that some of the legal requirements have not been addressed during the project concept preparation, which could result in significant financial penalties against the organization. The PM knows that implementation of appropriate changes is costly and will exceed the budget and scope of the project. Which of the following should the PM do FIRST?

Options:

A.

Escalate the finding to the change control board.

B.

Add a risk to the risk register for validation.

C.

Consult the RACI matrix to identify ownership of the risk.

D.

Have a meeting with the project sponsor and main stakeholders.

Buy Now
Question # 95

During the execution phase, user accepted testing failed; nonetheless, the vendor PM is insisting that the program manager approve the invoice for this phase. Which of the following actions should the Program manager take?

Options:

A.

Escalate the issue with the project sponsor and ask for assistance in managing the situation.

B.

Work with the vendor to achieve a compromise that benefits everyone.

C.

Approve the invoice to avoid damaging the relationship with the vendor.

D.

Schedule a call with the vendor PM and vendor executive to review the statement of work.

Buy Now
Question # 96

A developer recommends modifying an existing portion of code that is not part of the scope and is causing low performance on the current solution. Which of the following actions should the project manager most likely take?

Options:

A.

Ask a developer to create a change request.

B.

Do nothing because recommendation is scope creep.

C.

Ask a developer to implement the recommendation.

D.

Communicate the change status.

Buy Now
Question # 97

Although a project was successfully released into production a month ago, a project manager continues to receive project-related work. Which of the following is the reason for this issue?

Options:

A.

The project manager did not release the resources.

B.

The project is in the verification testing phase.

C.

The project manager did not complete the project closure phase.

D.

The project manager did not remove access.

Buy Now
Question # 98

A project manager is eager to define access requirements during the initiation phase of a project. Which of the following steps should the project manager perform first?

Options:

A.

Define the WBS.

B.

Develop a RAM.

C.

Manage the vendors.

D.

Assess the resource pool.

Buy Now
Question # 99

A key stakeholder recommends to a senior developer that a new feature be added. The new feature is not part of the current requirement documentation. Which of the following is MOST likely happening?

Options:

A.

Scope creep

B.

Collecting requirements

C.

Decision-making

D.

Project change

Buy Now
Question # 100

During the execution phase of a project, team members have been constantly disagreeing about the tasks they have been assigned. Which of the following is most likely the reason they are disagreeing?

Options:

A.

Some work packages are missing from the WBS.

B.

Information is missing from the RACI matrix.

C.

New knowledge bases were introduced.

D.

Team touch points are missing.

Buy Now
Question # 101

Which of the following is the best example of CapEx?

Options:

A.

Taxes

B.

Vehicles

C.

Salaries

D.

Utilities

Buy Now
Question # 102

In a functional organization, a project has been completed successfully. Which of the following actions would the project manager MOST likely perform?

Options:

A.

Assemble a new project with existing resources.

B.

Obtain the final report from release management.

C.

Notify the functional manager that resources are released.

D.

Allocate resources in a different project

Buy Now
Question # 103

A stakeholder works in a remote location and has not been replying to emails. The Internet service in that location is intermittent, and the stakeholder prefers to be contacted by telephone. Which of the following artifacts should the project manager have prepared to avoid this situation?

Options:

A.

Responsibility assignment matrix

B.

Acceptable communication channels

C.

Risk registry

D.

Staff directory

Buy Now
Exam Code: PK0-005
Exam Name: CompTIA Project+ Certification (2025)
Last Update: Jun 20, 2025
Questions: 362
PK0-005 pdf

PK0-005 PDF

$34  $84.99
PK0-005 Engine

PK0-005 Testing Engine

$38  $94.99
PK0-005 PDF + Engine

PK0-005 PDF + Testing Engine

$54  $134.99