Weekend Special Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: bigdisc65

PK0-005 Exam Dumps - CompTIA Project+ Questions and Answers

Question # 84

A project manager buys an extended warranty for a set of servers. Which of the following risk management strategies is the manager using?

Options:

A.

Transfer

B.

Avoid

C.

Accept

D.

Mitigate

Buy Now
Question # 85

A client made a change request. Implementing the change will cause a delay in the project and a budget overrun. Which of the following should the project manager do first?

Options:

A.

Update the WBS.

B.

Escalate to the CCB.

C.

Accept the change.

D.

Implement the change.

Buy Now
Question # 86

A project team was instructed to refurbish old desktops. The following provides the details of the issues observed:

Which of the following issues should be addressed FIRST?

Options:

A.

Replace missing peripherals because this process can be easy and less costly.

B.

An old operating system issue has the most amount of occurrences.

C.

Damage to the monitor has the highest percentage.

D.

Address each issue as discovered to avoid rework.

Buy Now
Question # 87

A project manager learns that a handful of resources from the project were pulled off the project to work on a higher priority project. The project manager had previously captured this information based on indicators of this potential change. Which of the following is the sequence of these events?

Options:

A.

Issue, issue

B.

Issue, risk

C.

Risk, issue

D.

Risk, risk

Buy Now
Question # 88

Which of the following provides a layered approach to logging in to systems that contain an organization's most valuable intellectual property?

Options:

A.

Remote access

B.

Password protection

C.

Multifactor authentication

D.

Virtual private network

Buy Now
Question # 89

A development team, which is working on a software project demonstrates software functionality 10 project stakeholder a week before the implementation date. Several stakeholders comment that the software does not meet the communicated expectations. Which of the following tools should the project manager use to validate the functionality?

Options:

A.

Project status report

B.

Requirements Traceability Matrix

C.

Detect log

D.

Signed project charter

E.

Work breakdown structure

Buy Now
Question # 90

As part of a global project, the project manager wants to ensure there is no disruption in the day-to-day performance among project team members around the world Which of the following should the project manager consider doing as part of the project planning?

Options:

A.

Monitoring the project team

B.

Creating a handoff process

C.

Colocating the project team

D.

Creating a separate statement of work

Buy Now
Question # 91

A project team is developing an application that will allocate a building's parking spaces. The building owner does not agree with using corporate colors in the application and has blocked

the release of the beta version for testing. Which of the following best describes what the project manager should have done in the initiation phase to prevent this issue?

Options:

A.

Review of existing artifacts

B.

Development of an issue log

C.

Identification and assessment of stakeholders

D.

Establishment of accepted communication channels

Buy Now
Question # 92

Halfway through a project, the sponsor states that the project is taking too long to complete. Which of the following should the project manager consult?

Options:

A.

Gantt chart

B.

Maintenance window schedule

C.

Functional requirements

D.

Test results

Buy Now
Question # 93

A project is running over budget, and due to new legislation in the country, the company needs to release all its contractors on the project or hire them as full-time employees. Which of the following should the PM do next to comply with the new legislation?

Options:

A.

Use only full-time employees even if the project is delayed.

B.

Hire all team members to avoid any delay in the project.

C.

Close the contract and pay the contractors cash for the remainder of the project.

D.

Look for an overseas vendor to finalize the project work.

Buy Now
Exam Code: PK0-005
Exam Name: CompTIA Project+ Certification (2025)
Last Update: Jun 14, 2025
Questions: 362
PK0-005 pdf

PK0-005 PDF

$29.75  $84.99
PK0-005 Engine

PK0-005 Testing Engine

$33.25  $94.99
PK0-005 PDF + Engine

PK0-005 PDF + Testing Engine

$47.25  $134.99