Spring Sale 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: Board70

PK0-005 Exam Dumps - CompTIA Project+ Questions and Answers

Question # 114

A highly scored negative risk causes a risk trigger, but the issue has not started yet. Which of the following is the next step the project team should take?

Options:

A.

Execute the contingency plan

B.

Perform a work-around

C.

Escalate to senior management

D.

Assign a risk owner

Buy Now
Question # 115

A car manufacturer is presenting to three vendors the abilities and qualifications required to develop the last module of a data warehouse application. The manufacturer is emphasizing the technical skills necessary to complete the project on time and highlighting its current internal IT project. Which of the following best describes this activity?

Options:

A.

Key stakeholder identification

B.

Preliminary procurement

C.

Solution design determination

D.

Critical factor enlistment

Buy Now
Question # 116

A project manager has decided to wait until all requirements are developed to initiate testing. Which of the following relationship dependencies is the project manager using?

Options:

A.

Start-to-finish

B.

Finish-to-finish

C.

Finish-to-start

D.

Start-to-start

Buy Now
Question # 117

A project's QA team needs to validate functionality in a timely and cost-effective way to ensure good coverage every time a new change is integrated. Which of the following test should the team execute?

Options:

A.

Sanity

B.

Manual

C.

Automated

D.

Regression

Buy Now
Question # 118

A project manager distributes minutes after each project meeting. However, the project manager is having difficulties hosting the meetings and documenting the discussions simultaneously. Which of the following should the project manager do in order to be most efficient?

Options:

A.

Assign a scribe to take notes.

B.

Record the meeting and transcribe the notes later.

C.

Instruct each team member to take notes.

D.

Get a facilitator for the meetings.

Buy Now
Question # 119

A project manager requests the testing team to figure out if a website allows multiple users to be signed in at the same time. Which of the following testing methods would be best for the testing team to use?

Options:

A.

Regression

B.

Unit

C.

Stress

D.

Smoke

Buy Now
Question # 120

A project manager and team are currently in the planning phase of a project. Which of the following should the team do during this phase?

Options:

A.

Identify and assess stakeholders.

B.

Hold daily status meetings.

C.

Remove access and plan the project sign-off.

D.

Review assumptions and constraints for input to the risk register.

Buy Now
Question # 121

Which of the following is a capital expense?

Options:

A.

Building lease

B.

Building purchase

C.

Building maintenance

D.

Building insurance

Buy Now
Question # 122

Which of the following aspects are true of agile as compared to waterfall? (Select two).

Options:

A.

Agile works through larger integrated teams.

B.

Agile promotes project manager ownership over deliverables.

C.

Agile reinforces the importance of comprehensive documentation.

D.

Agile has more customer involvement throughout development.

E.

Agile is more flexible to allow for changes in scope.

F.

Agile is comprised of well-defined phases.

Buy Now
Question # 123

Which of the following statements best describes zero-based budgeting?

Options:

A.

Start with the budget from the last project and add any new expenses.

B.

Start with allocating expenses based on the importance of the project.

C.

Start the project with a fixed amount decided by the management team.

D.

Start with no financial plan and justify each new expense.

Buy Now
Exam Code: PK0-005
Exam Name: CompTIA Project+ Certification (2026)
Last Update: Mar 11, 2026
Questions: 447
PK0-005 pdf

PK0-005 PDF

$25.5  $84.99
PK0-005 Engine

PK0-005 Testing Engine

$28.5  $94.99
PK0-005 PDF + Engine

PK0-005 PDF + Testing Engine

$40.5  $134.99