Question # 44

Which of the following statements is false?

Options:

A.

Uncertainty and risk are greatest at the start of the project and lowest at the end.

B.

The amount at stake Is lowest at the end of the project and greatest at the start.

C.

Expected monetary value can be expressed as the product of the risk event probability and the risk event value.

D.

Opportunities are positive outcome of risks.

Buy Now
Question # 45

The one document that should always be used to help identify risk is _______.

Options:

A.

Risk Management Plan

B.

WBS

C.

Scope Statement

D.

Project Charter

Buy Now
Question # 46

Which of the following is considered during the Plan Procurement Process?

Options:

A.

Whether to procure

B.

How to procure and how much to procure

C.

What and when to procure

D.

All of the above

Buy Now
Question # 47

On a project, quality should generally be of ________.

Options:

A.

Equal priority with schedule, but higher priority than cost

B.

Higher priority than cost and schedule

C.

Equal priority with cost, but higher priority than schedule

D.

Equal priority with cost and schedule

Buy Now
Question # 48

The adjustment of task schedules in order to deploy human resource more effectively is called resource _______.

Options:

A.

Tracking

B.

Loading

C.

Crashing

D.

Levelling

Buy Now
Question # 49

A is the correct answer. Trend analysis is a tool and technique used in Monitor and Control Risks.

Options:

A.

Financial records

B.

Inspection specifications

C.

Project charter

D.

Project reports

Buy Now
Question # 50

Which of the following is true concerning the evaluation criteria?

Options:

A.

Can often be found in procurement documents

B.

Can be objective or subjective

C.

Used to rate or score proposals

D.

All of the above

Buy Now
Question # 51

Which of the following is conflict resolution technique?

Options:

A.

Compromise

B.

Smoothing

C.

Foimal

D.

Coercive

Buy Now
Question # 52

How many communication channels exist in a team of 10 members?

A) 45

B) 10

C) 30

D 20

Options:

Buy Now
Question # 53

How many communication channels will be required in a project in which 5 individual are participating?

Options:

A.

10

B.

12

C.

4

D.

5

Buy Now
Exam Code: PMI-002
Exam Name: Certified Associate in Project Management (CAPM) Certification
Last Update: Aug 22, 2025
Questions: 748
PMI-002 pdf

PMI-002 PDF

$29.75  $84.99
PMI-002 Engine

PMI-002 Testing Engine

$33.25  $94.99
PMI-002 PDF + Engine

PMI-002 PDF + Testing Engine

$47.25  $134.99