Question # 64

________ must be measured regularly to identify variance from the plan.

Options:

A.

Project performance

B.

Stakeholder requirements

C.

Schedule progress

D.

Cost and schedule

Buy Now
Question # 65

In which of the following organizations the project manager role is likely to be part-time?

Options:

A.

Weak matrix

B.

Functional

C.

Balanced matrix

D.

Both A and B

Buy Now
Question # 66

Formal acceptance by the client or sponsor of the project should be prepared and distributed during which process?

Options:

A.

Distribute Information

B.

Administrative Closeout

C.

Organizational Planning

D.

Report Performance

Buy Now
Question # 67

A technique for resolving conflict in which the parties agree to have a neutral third party hear the dispute and make a decision is called ____________.

Options:

A.

Negotiation

B.

Arbitration

C.

Smoothing

D.

Forcing

Buy Now
Question # 68

If a project has an 80% chance of having the scope defined by a certain date and a 70% chance of obtaining approval for the scope by a certain date, what is the probability of both events occurring?

Options:

A.

75%

B.

65%

C.

50%

D.

56%

Buy Now
Question # 69

You are project manager and now in middle of creating RFP (Request for proposal). RFP (Request for proposal) is done in _______.

Options:

A.

Plan Procurements

B.

Conduct Procurements

C.

Administer Procurements

D.

Close Procurements

Buy Now
Question # 70

You are the project manager of a project. If there are approved changes to the original scope, what you do with the old original scope?

Options:

A.

Save the old versions

B.

No need to save old version

C.

Scrap the old version

D.

Old version is not required

Buy Now
Question # 71

When the version control numbers should change?

Options:

A.

Any change occurs

B.

Major changes are made

C.

Any change related to scope only

D.

Only if minor changes are made

Buy Now
Question # 72

From whom do you need to gain the formal acceptance at project closure?

Options:

A.

The customer

B.

The qualify director

C.

Project management office

D.

Project manager

Buy Now
Question # 73

Which of the following are the outputs of Collect Requirements Process?

Options:

A.

Requirements documentation

B.

Requirements management plan

C.

The requirements tractability matrix

D.

Al1 of the above

Buy Now
Exam Code: PMI-002
Exam Name: Certified Associate in Project Management (CAPM) Certification
Last Update: Aug 22, 2025
Questions: 748
PMI-002 pdf

PMI-002 PDF

$29.75  $84.99
PMI-002 Engine

PMI-002 Testing Engine

$33.25  $94.99
PMI-002 PDF + Engine

PMI-002 PDF + Testing Engine

$47.25  $134.99