Weekend Special Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: bigdisc65

PMI-002 Exam Dumps - PMI CAPM Questions and Answers

Question # 74

Using the PMBOK definition of contingency reserve, which of the following statements about contingency reserves is false?

Options:

A.

A contingency reserve is a separately planned quantity used to allow for future situations which may be planned for only in part.

B.

Contingency reserves may be set aside for known unknowns.

C.

Contingency reserves may be set aside for unknown unknowns.

D.

Contingency reserves are normally included in the project's cost and schedule baselines.

Buy Now
Question # 75

Which of the following statements are FALSE about cost reimbursable contracts?

Options:

A.

cost-reimbursable contracts generally carry the highest risks to the buyer, as the total costs are uncertain

B.

cost-reimbursable contracts often includes incentives for meeting or exceeding project objectives

C.

cost-reimbursable contracts resemble fix unit agreements when the unit rates are preset by the buyer and seller

D.

cost-reimbursable contracts are contracts that involves payments to the seller for actual costs, plus a fee representing the sellers profit

Buy Now
Question # 76

After preparing a probability distribution of cost outcomes for a project, the estimate with a 20% probability of being exceeded is approximately one standard deviation:

Options:

A.

Below the mean.

B.

Above the mean.

C.

Below the median.

D.

Above the median.

Buy Now
Question # 77

A response to a risk event that was not defined in advance of is occurrence is called a:

Options:

A.

Risk mitigation response.

B.

Workaround response.

C.

Corrective action response.

D.

Contingency response.

Buy Now
Question # 78

Which of the following statements concerning compromise as a conflict resolution is false?

Options:

A.

Neither party wins but both parties get some degree of satisfaction.

B.

Important aspects of the project may be hindered in order to achieve personal objectives.

C.

Compromise is generally considered a lose-lose situation.

D.

A definitive resolution is seldom achieved.

Buy Now
Question # 79

You have a piece of equipment that was purchased for your ptoject recently for $5,000 and is expected to last 5 years in production. At the end of the five years the expected worth of the equipment is $2,000. Using straight-line deprecation, what is the amount that can be written off each year?

Options:

A.

$600

B.

$1200

C.

$3000

D.

Zero

Buy Now
Question # 80

Which of the following statements are false about Expected Monetary Value Analysis (EMV).

Options:

A.

EMV is a statistical concept that calculates the average outcome of project outcomes based on various assumptions and scenarios.

B.

Decision tree analysis is a type of EMV analysis.

C.

EMV is a tool/technique of Perform Qualitative Risk Analysis.

D.

EMV is calculated by multiplying the value of each possible outcome by its probability of occurrence, and summing them together.

Buy Now
Question # 81

The sending or conveying of information from one place to another is the process of _______________.

Options:

A.

Networking

B.

Transmitting

C.

Encrypting

D.

Promoting

Buy Now
Question # 82

Which one of the following is not an output of contract closure?

Options:

A.

c'ose contracts

B.

Lessons learned documentation

C.

Deliverable acceptance

D.

Scope statement

Buy Now
Question # 83

Which of the following situations will cause schedule activity duration estimates to directly influence the cost estimates EXCEPT:

Options:

A.

When resource cost rate information is unavailable from commercial databases

B.

When resources are applied per unit of time of duration of schedule activity

C.

When union labor with regularly expiring collective bargaining agreements are involve

D.

When seasonal cost variations are involve

E.

When project budget includes interest rate changes

Buy Now
Exam Code: PMI-002
Exam Name: Certified Associate in Project Management (CAPM) Certification
Last Update: Aug 22, 2025
Questions: 748
PMI-002 pdf

PMI-002 PDF

$29.75  $84.99
PMI-002 Engine

PMI-002 Testing Engine

$33.25  $94.99
PMI-002 PDF + Engine

PMI-002 PDF + Testing Engine

$47.25  $134.99