Weekend Special Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: bigdisc65

PMI-SP Exam Dumps - PMI Certification Questions and Answers

Question # 24

You work as a Project Manager for Dreams Unlimited Inc. You are looking for performance efficiencies of a project. The related key values are provided in the table below:

MeasurementsValues

BCWP (or EV)325

BCWS (or PV) 300

ACWP (or AC)410

What will be the cost performance index (CPI) of the project at the current point of time?

Options:

A.

0.923

B.

1.083

C.

1.261

D.

0.792

Buy Now
Question # 25

Harry works as the project manager for his organization. He is creating the activity list and would like to tag those activities that are comprised of apportioned effort. Which of the following is the best example of apportioned effort?

Options:

A.

Adding features to the project's product that is not included in the project scope.

B.

Managing the day-to-day events of a project.

C.

Creating software as defined in the project scope.

D.

Completing project activities as start-to-start events.

Buy Now
Question # 26

You are the project manager of the GHY Project. This project is scheduled to last for one year and has a BAC of $4,500,000. You are currently 45 percent complete with this project, though you are supposed to be at your second milestone which accounts for half of the project completion. There have been some errors in the project which has caused you to spend $2,073,654. What is this project's schedule performance index?

Options:

A.

1.02

B.

0.98

C.

0.90

D.

-$108,120

Buy Now
Question # 27

Fred is the project manager of the NHA project. This project has a BAC of $2,456,900 and is sixty percent complete. Fred has crashed the project, which has driven the project costs to date to $1,525,140, but his project is five percent more complete than what was planned. What is the cost variance for this project that Fred needs to report to management?

Options:

A.

$122,845

B.

-$51,000

C.

-$85,000

D.

Zero

Buy Now
Question # 28

Marty is the project manager of the recently completed NHK Project. The project was deemed successful by the project customer and they have signed the formal acceptance documentation. Marty has written the final project report, released the project team, and completed the lessons learned documentation. What else should Marty do in the closure of the NHK Project?

Options:

A.

Archive the project records.

B.

Summarize the project risks costs.

C.

Summarize the project variance.

D.

Close the project office.

Buy Now
Question # 29

Which of the following documents is a narrative description of products or services to be supplied by the project and has detailed requirements and pricing specified on it?

Options:

A.

Scope of statement

B.

Project charter

C.

Statement of work (SOW)

D.

WBS

Buy Now
Question # 30

Lily works as a project manager for BlueWell Inc. She has recorded the following duration estimates for an activity in her project: optimistic 35, most likely 50, and pessimistic 95. What time will she record for this activity?

Options:

A.

48

B.

55

C.

54

D.

40

Buy Now
Question # 31

Fill in the blank with an appropriate phrase.

The __________ includes a description of any collateral services required, such as performance reporting or post-project operational support for the procured item.

Options:

Buy Now
Question # 32

Holly is the project manager for her organization. In her project, she has worked with the project team to define when the project team will be utilized in the project, the duration of the project activities, and the sequence in which the project work must be completed. During several phases of her project, the project team will need to work more than fifty hours per week. The project team members have agreed this is necessary and they're willing to do the work to complete the project. Management, however, has not approved Holly's schedule based on the overtime the scheduling will require. They have set a limit on the project schedule of 45 hours per week. What is this limit technically called? Each correct answer represents a complete solution. Choose all that apply.

Options:

A.

Constraint

B.

Assumption

C.

Execution variance analysis

D.

Resource leveling heuristic

Buy Now
Question # 33

You are the project manager of the NHA Project. This project is expected to last one year with quarterly milestones throughout the year. Your project is supposed to be at the third milestone today but you're likely only 60 percent complete. Your project has a BAC of $745,000 and you've spent $440,000 of the budget-to-date. What is your schedule performance index for this project?

Options:

A.

80

B.

1.02

C.

102

D.

0.80

Buy Now
Exam Code: PMI-SP
Exam Name: PMI Scheduling Professional
Last Update: Aug 22, 2025
Questions: 323
PMI-SP pdf

PMI-SP PDF

$29.75  $84.99
PMI-SP Engine

PMI-SP Testing Engine

$33.25  $94.99
PMI-SP PDF + Engine

PMI-SP PDF + Testing Engine

$47.25  $134.99