Weekend Special Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: bigdisc65

PMI-SP Exam Dumps - PMI Certification Questions and Answers

Question # 4

Anna is the project manager of the NHQ project. Her project has 1,500 stakeholders, some of which are external to her organization. In this project, Anna wants to create a method to classify the stakeholders based on their level of authority and their level of concern regarding the project outcomes. This model will help Anna determine the communication demands and when information should be distributed. What does Anna want to create in this instance?

Options:

A.

Power/interest grid

B.

Salience model

C.

Power/influence grid

D.

Communications matrix

Buy Now
Question # 5

Which of the following components of the change control system includes the documentation, tracking systems, and defined approval levels necessary for authorizing and controlling changes?

Options:

A.

Scope Verification

B.

Configuration Management System

C.

Project Management Information System

D.

Integrated Change Control

Buy Now
Question # 6

Examine the figure given below:

You are the project manager of this project. Tom, a project team member, reports that Activity D will be delayed by 12 days due to the unavailability of the resources from the vendor. What will this delay do to your project completion, if you allow the delay to enter into the project?

Options:

A.

The project will be one day late.

B.

The float for activity D will be consumed.

C.

The project can still finish on time.

D.

The project will be seven days late.

Buy Now
Question # 7

You work as a project manager for BlueWell Inc. You and your project team is undergoing the decision making process for the project. You want to involve key participants to gain acceptance and commitment to make the solution work. Which of the following phases of the decision- making model defines this process of work?

Options:

A.

Ideas to action

B.

Problem definition

C.

Problem solution generation

D.

Solution action planning

Buy Now
Question # 8

Harry is the project manager of a large network installation project. This project requires Harry to add network cable to each office and cubicle of a 14-story office building. Harry will receive a bonus for good time and cost performance in this project. What law of economics would prevent Harry from exponentially adding labor to the project work in an effort to complete the work in a very small amount of time?

Options:

A.

Parkinson's Law

B.

Law of Diminishing Returns

C.

Law of Economics

D.

Moore's Law

Buy Now
Question # 9

You work as a project manager for BlueWell Inc. You have to identify the specific actions to be performed to produce the project deliverables. For this, you have to explain the three inputs for the define activities process to your project team. Which of the following is NOT a valid input?

Options:

A.

Work Breakdown Structure

B.

Enterprise Environmental Factors

C.

Scope baseline

D.

Organizational Process Assets

Buy Now
Question # 10

You are the project manager of the NHQ project. This project is slightly larger than the TR project, in which you also served as the project manager. You decide to use the actual activity duration of the GTR project as a basis for your current NHQ project. This, you reason, will save time for your project, as the previous project has provided the information. Which one of the following terms best describes the action you are doing in this scenario?

Options:

A.

You are creating an analogous estimate.

B.

You are creating a bottom-up estimate.

C.

You are relying on expert judgment.

D.

You are creating a rough order of magnitude estimate.

Buy Now
Question # 11

You are the project manager for your organization. You are working through the control schedule process. According to the PMBOK, there are four inputs to this process. Which one of the following is NOT an input to the control schedule process?

Options:

A.

Schedule data

B.

Work performance information

C.

Project management plan

D.

Project schedule

Buy Now
Question # 12

Mary is the project manager of the H1QZ Project. This project is a subproject of the HQZ Project and the project schedule is fixed and cannot vary. Stephen, a project team member, reports that he's having trouble completing his project assignment and will likely be at least two days late. Examine the figure given below:

If Stephen's assignment is Activity B, what impact will his two days of lateness have on the project end date?

Options:

A.

The project will complete on time.

B.

The project will be late by one day.

C.

The project will be late by two days.

D.

The project will be early by two days.

Buy Now
Question # 13

A project manager is reviewing her project performance. Her project has a BAC of $950,000 and is currently 40 percent complete, though it was scheduled to be 45 percent complete at this time. Her project has spent $387,526. Management would like to know if there is a schedule variance. What is the planned value for this project?

Options:

A.

-$47,500

B.

0.89

C.

$427,500

D.

0.98

Buy Now
Exam Code: PMI-SP
Exam Name: PMI Scheduling Professional
Last Update: Aug 22, 2025
Questions: 323
PMI-SP pdf

PMI-SP PDF

$29.75  $84.99
PMI-SP Engine

PMI-SP Testing Engine

$33.25  $94.99
PMI-SP PDF + Engine

PMI-SP PDF + Testing Engine

$47.25  $134.99