Anna is the project manager of the NHQ project. Her project has 1,500 stakeholders, some of which are external to her organization. In this project, Anna wants to create a method to classify the stakeholders based on their level of authority and their level of concern regarding the project outcomes. This model will help Anna determine the communication demands and when information should be distributed. What does Anna want to create in this instance?
Which of the following components of the change control system includes the documentation, tracking systems, and defined approval levels necessary for authorizing and controlling changes?
Examine the figure given below:
You are the project manager of this project. Tom, a project team member, reports that Activity D will be delayed by 12 days due to the unavailability of the resources from the vendor. What will this delay do to your project completion, if you allow the delay to enter into the project?
You work as a project manager for BlueWell Inc. You and your project team is undergoing the decision making process for the project. You want to involve key participants to gain acceptance and commitment to make the solution work. Which of the following phases of the decision- making model defines this process of work?
Harry is the project manager of a large network installation project. This project requires Harry to add network cable to each office and cubicle of a 14-story office building. Harry will receive a bonus for good time and cost performance in this project. What law of economics would prevent Harry from exponentially adding labor to the project work in an effort to complete the work in a very small amount of time?
You work as a project manager for BlueWell Inc. You have to identify the specific actions to be performed to produce the project deliverables. For this, you have to explain the three inputs for the define activities process to your project team. Which of the following is NOT a valid input?
You are the project manager of the NHQ project. This project is slightly larger than the TR project, in which you also served as the project manager. You decide to use the actual activity duration of the GTR project as a basis for your current NHQ project. This, you reason, will save time for your project, as the previous project has provided the information. Which one of the following terms best describes the action you are doing in this scenario?
You are the project manager for your organization. You are working through the control schedule process. According to the PMBOK, there are four inputs to this process. Which one of the following is NOT an input to the control schedule process?
Mary is the project manager of the H1QZ Project. This project is a subproject of the HQZ Project and the project schedule is fixed and cannot vary. Stephen, a project team member, reports that he's having trouble completing his project assignment and will likely be at least two days late. Examine the figure given below:
If Stephen's assignment is Activity B, what impact will his two days of lateness have on the project end date?
A project manager is reviewing her project performance. Her project has a BAC of $950,000 and is currently 40 percent complete, though it was scheduled to be 45 percent complete at this time. Her project has spent $387,526. Management would like to know if there is a schedule variance. What is the planned value for this project?