Summer Special Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: bigdisc65

PRINCE2 Certification Prince2-Practitioner Exam Dumps

Page: 2 / 10
Question 8

Scenario

A photographer from Portraits Ltd, a professional photographic company, has taken on the role of Team Manager after taking some time to understand the requirements of the project. A contract for their services has been set up and is being monitored by the Purchasing Manager and a Work Package has been agreed. This contract specifies that the photographer must arrange a meeting with the Engineering Manager to establish a schedule for the photo sessions to minimize the impact on the Engineering staff. This meeting should have occurred by now.

The Engineering Manager was made aware of this requirement but when asked he reported that he has received no communication from the photographer. The Project Manager has tried to call the photographer and has had no response. The Project Manager believes there is a risk that Portraits Ltd are overbooking work and prioritizing other clients' work. If Portraits ltd do not deliver on schedule the project will be delayed and the expected benefits will be reduced.

The contract is to be reviewed and Portraits Ltd reminded of their agreement.

The project is now in stage 2. The Project Manager has heard about the possibility of a competitor also producing a calendar to be delivered earlier than the target date for this project. There is a threat that the early release of a competitor's calendar may weaken the impact of the MNO Manufacturing Company calendar, thereby reducing the anticipated benefits of the Calendar project.

Which 2 statements should be recorded under the Timing of risk management activities heading?

Options:

A.

During stage 4, the selected service provider will manage any risks to their Business Case and report these to the Project Manager on a weekly basis.

B.

The Project Board should hold monthly meetings to review project progress.

C.

When closing a project, the follow-on action recommendations should be updated with any risks relating to the realization of benefits after the outsourced services go live.

D.

Any new risks identified during product development should be reported to the Project Manager by the Team Manager when delivering the completed Work Package.

E.

When authorizing a stage, the Project Board will check that the exposure to risk is still acceptable.

Question 9

Scenario

Additional Information

Chief Executive Officer (CEO): He started the company 25 years ago and knows his job very well. He injured his leg two years ago which has restricted his visits to the engineering area. As CEO he has an overall perspective of the business strategic requirements and the authority to commit resources as required.

Marketing Director: She has been with the company for three years, following a successful career with a publicity company. She has the ability to represent the needs of the business, particularly as this is a marketing project. She has the authority to commit the annual business marketing budget, from which the project will be funded, as she sees appropriate. She will be responsible for monitoring the expected benefits of the calendar, in particular the improvement of the company's image.

Engineering Manager: He has been responsible for many engineering innovations in the company and is still as keen and energetic as the day he started. VVhilst he will not be part of the project team, his staff will feature in the photos for the promotional calendar.

Central Records: This group of five staff looks after all company records and document control. They now maintain all project files.

Bright Lights: This is the local office supplies company. It supplies all the stationery and office equipment needs of the company and will supply the stationery for this project.

Portraits ltd: This is a professional photographic company with a number of excellent photographers and a history of successful work. This company has been selected to take the photos for the company calendar. It has yet been decided which of the photographers to use.

Which 2 statements explain why the Marketing Director should be appointed as a Senior User for this project?

Options:

A.

She can represent the Marketing department.

B.

She previously had a successful career in publicity.

C.

The Marketing department will help to deliver the benefits of this project.

D.

The project will be funded from the business marketing budget.

E.

A number of the products will be produced by the Sales department and the Marketing department.

Question 10

Scenario

Additional Information

Chief Executive Officer (CEO): He started the company 25 years ago and knows his job very well. He injured his leg two years ago which has restricted his visits to the engineering area. As CEO he has an overall perspective of the business strategic requirements and the authority to commit resources as required.

Marketing Director: She has been with the company for three years, following a successful career with a publicity company. She has the ability to represent the needs of the business, particularly as this is a marketing project. She has the authority to commit the annual business marketing budget, from which the project will be funded, as she sees appropriate. She will be responsible for monitoring the expected benefits of the calendar, in particular the improvement of the company's image.

Engineering Manager: He has been responsible for many engineering innovations in the company and is still as keen and energetic as the day he started. VVhilst he will not be part of the project team, his staff will feature in the photos for the promotional calendar.

Central Records: This group of five staff looks after all company records and document control. They now maintain all project files.

Bright Lights: This is the local office supplies company. It supplies all the stationery and office equipment needs of the company and will supply the stationery for this project.

Portraits ltd: This is a professional photographic company with a number of excellent photographers and a history of successful work. This company has been selected to take the photos for the company calendar. It has yet to be decided which of the photographers to use.

Which 2 statements explain why the Purchasing Manager should be appointed as a Senior Supplier for this project?

Options:

A.

He is responsible for the organization's procurement activates.

B.

He is responsible for the performance of supplier contracts.

C.

He was an engineer and worked in that area before taking up his current position.

D.

He can influence the external supplier's Business Case.

E.

He is not appropriate for the role of Executive or Senior User.

Question 11

Which of the following is False?

A Successful project management team should.

Options:

A.

Have business, user and supplier stakeholder representation

B.

Never be reviewed as members should stay with the team for the duration

C.

Ensure appropriate governance by defining responsibilities for directing, managing and delivering the project and clearly defining accountability at all levels

D.

Have an effective strategy to manage communication flows to and from stakeholders

Page: 2 / 10
Exam Name: PRINCE2 Practitioner Exam
Last Update: May 19, 2024
Questions: 282
Prince2-Practitioner pdf

Prince2-Practitioner PDF

$28  $80
Prince2-Practitioner Engine

Prince2-Practitioner Testing Engine

$33.25  $95
Prince2-Practitioner PDF + Engine

Prince2-Practitioner PDF + Testing Engine

$45.5  $130