Question # 14

You are using DMO of SUM. You defined 40 parallel R3load processes during uptime and 80 parallel R3load processes during downtime. The server provides 8 CPU cores. Phase EU_CLONE_MIG_DT_RUN is running. In the Charts Control Center, you can see 40 process buckets being executed in parallel. Why are 40 Process Buckets executed in parallel?

Options:

A.

These are 40 pairs of R3load processes, so there are 80 R3load processes running.

B.

There is a maximum of 40 parallel R3load processes within this specific phase.

C.

SUM is still running in uptime; the 40 defined R3load processes are considered.

D.

The number of CPU cores does NOT allow more than 40 R3load processes to be run in parallel.

Buy Now
Question # 15

You are performing an inplace SAP S/4HANA conversion including DMO. What is the latest point in time when you can reset the procedure without losing data?

Options:

A.

The end of the database migration

B.

The start of the Execution roadmap step

C.

The end of the business downtime

D.

The start of the business downtime

Buy Now
Exam Code: E_S4CON_2505
Exam Name: SAP Certified Specialist - SAP S/4HANA Conversion and SAP System Upgrade
Last Update: Nov 5, 2025
Questions: 40
E_S4CON_2505 pdf

E_S4CON_2505 PDF

$29.75  $84.99
E_S4CON_2505 Engine

E_S4CON_2505 Testing Engine

$33.25  $94.99
E_S4CON_2505 PDF + Engine

E_S4CON_2505 PDF + Testing Engine

$47.25  $134.99