Spring Sale 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: Board70

PK0-005 Exam Dumps - CompTIA Project+ Questions and Answers

Question # 34

Which of the following criteria would favor using the agile methodology to manage an upcoming project?

Options:

A.

Strong projectized organization

B.

Medium risk

C.

Lack of resources

D.

Multiple undefined tasks

Buy Now
Question # 35

While working with a contractor, the project manager identified a communication conflict. The contractor did not agree that there was an issue. Which of the following should the project manager and contractor review?

Options:

A.

Scope of work

B.

Request for proposal

C.

Vendor rules of engagement

D.

Project schedule

Buy Now
Question # 36

Which of the following is a reason to use a SOW on a project?

Options:

A.

To find out the contact information for the vendors

B.

To review the list of stakeholders

C.

To ensure the team stays within the scope of the contract

D.

To give explicit instruction on how to execute the work

Buy Now
Question # 37

Which of the following requires the MOST availability from the business team?

Options:

A.

SDLC

B.

Scrum

C.

PRINCE2

D.

Waterfall

Buy Now
Question # 38

After a migration was completed and a financial system was deployed, users have been unable to issue payment orders. Which of the following should be implemented?

Options:

A.

Rollback plan

B.

Release plan

C.

Deployment plan

D.

Contingency plan

Buy Now
Question # 39

Which of the following is a disadvantage of a cloud model?

Options:

A.

Limited processing and storage capacity

B.

Limited expansion capability

C.

Longer latency time

D.

Higher dependency on the vendor

Buy Now
Question # 40

By developing a project schedule, a PM has already validated the constraints, outlined the duration of the tasks and the phases, and confirmed the proper sequence and flow of the project. Which of the following activities still needs to be performed to complete the schedule?

Options:

A.

Allocate resources.

B.

Determine the project budget

C.

Develop a communication plan.

D.

Establish baselines.

Buy Now
Question # 41

A project manager is in the process of evaluating the probability and impact of a risk by assigning numbers such as a monetary value. Which of the following is the project manager using?

Options:

A.

Monte Carlo simulation

B.

Root cause analysis

C.

Quantitative risk analysis

D.

Risk response analysis

Buy Now
Question # 42

A project manager is working on an existing, large, complex project that involves regulatory and environmental considerations. The development of a detailed project plan will be critical. Which of the following should the project manager do first?

Options:

A.

Review the project charter.

B.

Start the process of engaging the stakeholders.

C.

Arrange a kickoff meeting.

D.

Evaluate potential risks.

Buy Now
Question # 43

Several months after a project has ended, a project team member is still charging time to the project and is unable to charge time to new projects. Which of the following did the project manager neglect to do?

Options:

A.

Remove the team member's access.

B.

Release the project resources.

C.

Collect the stakeholders' feedback.

D.

Have the closeout report approved.

Buy Now
Exam Code: PK0-005
Exam Name: CompTIA Project+ Certification (2026)
Last Update: Mar 11, 2026
Questions: 447
PK0-005 pdf

PK0-005 PDF

$25.5  $84.99
PK0-005 Engine

PK0-005 Testing Engine

$28.5  $94.99
PK0-005 PDF + Engine

PK0-005 PDF + Testing Engine

$40.5  $134.99