Which of the following is NOT required when performing weekly or monthly schedule updates?
When resource leveling craft labor for a critical path schedule, the scheduler
Which of the following are NOT normally included in the project scope statement, either directly or by reference?
Theoretically construct a summary activity for activities 6001 through 6003. Identify the governing predecessor and successor activities for the hammock:

Which letter of the alphabet best approximates the graphical shape of a project's cumulative cost baseline, or budgeted cost of work scheduled?
If a cost estimate assumes that 240 hours will be expended on a given activity, and the projected crew size expected to perform that activity is 5 personnel working and 8-hour workday, what is the calculated duration for the activity?
When should the project documents be reviewed to assess their impact on the organization and administration of a project?