PSP Exam Dumps - AACE International Professional Level Certifications Questions and Answers

Question # 24

Determine the correct formula and date for the late start for the Activity 11001:

Options:

A.

LF of 11001 less 27 days plus 1 day equaling 14 Jan 2024

B.

LF of 1000 less 25 days equaling 16 Jan 2024

C.

LF of 11001 less duration of 11001 equaling 16 Jan 2024

D.

LF of 11001 less 25 days plus 1 day equaling 16 Jan 2024

Buy Now
Question # 25

Using the normal schedule, what is the early finish date and total float of Activity 10002?

Options:

A.

24 Nov 2023. and 24 days of tree float

B.

24 Dec 2023. and 24 days of tree float

C.

17 Dec 2023. and 4 days of total float

D.

21 Dec 2023. and 4 days of total float

Buy Now
Question # 26

How much Total Float does drafting the product manual have?

Options:

A.

15 workdays.

B.

0 workdays.

C.

10 workdays.

D.

5 workdays.

Buy Now
Question # 27

If a new hammock activity covering activities 6001 through 6003 is developed, what are governing predecessor and successor activities?

Options:

A.

Predecessor is Activity 4001. successor is Activity 9004

B.

Predecessor is Activity 8001, successor is Activity 5001

C.

Predecessor is Activity 5001, successor is Activity 8001

D.

Predecessor is Activity 4001, successor is Activity 9003

Buy Now
Question # 28

Assuming activities 2001 through 2004 comprise the same WBS element, construct a WBS summary activity for activities 2001 through 2004. Use the normal schedule, what is the cost of the activity?

Options:

A.

$289.000

B.

$321.000

C.

$193,000

D.

$327,000

Buy Now
Question # 29

STION NO: 146

Using the normal schedule and excluding general conditions, which activities are NOT on the critical path?

Options:

A.

6001, 8001, 9001. 9002, 9004. 9005

B.

7001, 8001, 9001. 9003. 9004. 10002

C.

5001,7001.8001,9001,9004,9005

D.

2003,8001.9001.9002,9005,10001

Buy Now
Question # 30

When reconstructing a CPM schedule electronically from a hardcopy, which of the following is NOT required to determine the critical path?

Options:

A.

Detailed listing of working days for each calendar used

B.

Predecessor and successor listing with logic type and lag duration, preferably sorted by activity ID

C.

Assigned party responsibility for each work task

D.

Tabular listing of activities showing duration, calendar ID, early and late dates

Buy Now
Question # 31

The project goals_________.

Options:

A.

are the foundation for breakdown structures

B.

are defined independent of any external stakeholder opinions

C.

quantify performance and interface requirements

D.

consider all aspects of the project

Buy Now
Question # 32

Activity 2003 started during the current reporting period and proceeded as planned with the normal schedule. If the remaining duration at the end of this period is ten workdays, then what is the earned value assignable to Activity 2003 in the pay estimate for this reporting period?

Options:

A.

$6,000

B.

$10.000

C.

$5,000

D.

$8,000

Buy Now
Question # 33

What is the free float for Activity F?

Options:

A.

3 months.

B.

0months.

C.

1months.

D.

2month.

Buy Now
Exam Code: PSP
Exam Name: Planning & Scheduling Professional (PSP) Exam
Last Update: Nov 2, 2025
Questions: 216