Determine the correct formula and date for the late start for the Activity 11001:

Using the normal schedule, what is the early finish date and total float of Activity 10002?
If a new hammock activity covering activities 6001 through 6003 is developed, what are governing predecessor and successor activities?
Assuming activities 2001 through 2004 comprise the same WBS element, construct a WBS summary activity for activities 2001 through 2004. Use the normal schedule, what is the cost of the activity?
STION NO: 146
Using the normal schedule and excluding general conditions, which activities are NOT on the critical path?
When reconstructing a CPM schedule electronically from a hardcopy, which of the following is NOT required to determine the critical path?
Activity 2003 started during the current reporting period and proceeded as planned with the normal schedule. If the remaining duration at the end of this period is ten workdays, then what is the earned value assignable to Activity 2003 in the pay estimate for this reporting period?