Question # 54

In a "crashed" schedule, which is a chain of activities that precede activity 2004?

Options:

A.

1001, 2001, 2002, 2003

B.

2001, 2002, 2003, 2007

C.

1001, 2002, 2003

D.

1001, 2002, 2002, 2003, 3001

Buy Now
Question # 55

Using the "normal" schedule, theoretically construct a hammock for activities 6001-6003. What is the duration of the hammock?

Options:

A.

407 days

B.

362 days

C.

255 days

D.

267 days

Buy Now
Question # 56

Of the following update procedures, which is the least important in achieving an accurate forecast for completion of a construction schedule?

Options:

A.

Estimating remaining durations of activities.

B.

The correct recording of actual start dates.

C.

Making "downstream" logic revisions as required.

D.

Entering the time impacts of delays and change orders.

Buy Now
Question # 57

What is the result of a forward pass calculation?

Options:

A.

Value of total float for individual activities

B.

Early start and early finish date for individual activities

C.

Value of free float for individual activities

D.

Critical path

Buy Now
Question # 58

Prior to the start of work, Management determined the need to make the Product available 10 workdays earlier than planned. Which activities need to be expedited?

Options:

A.

Product Testing. Manufacture Product and Package Product

B.

Product Testing and Manufacture Product

C.

Draft Product Manual. Proof Product Manual, and Print Product Manual

D.

Release tor Manufacture and Product Available

Buy Now
Question # 59

Time-scaled logic diagrams are

Options:

A.

Only calculated using a computer.

B.

The same as a pure-logic diagram.

C.

Used to calculate the most probable activity duration.

D.

Logic networks that are drawn to match the calendar.

Buy Now
Question # 60

Select the most appropriate explanation for use of a winter/wet weather seasonal calendar for use in this project?

Options:

A.

to highlight a time when there are more holidays and work therefore will be slower and there will be more absenteeism

B.

to denote a time during which work may not progress as fast as planned and cost and risk may be elevated

C.

to provide a key to co-a weather for safety meetings

D.

to show a difference in the calendar year

Buy Now
Question # 61

Free float is the

Options:

A.

Difference between the early dates and late dates of an activity.

B.

Amount of time the early start of an activity can be delayed without impacting the early start of the successor activity.

C.

Difference between the early finish dates and late finish dates of an activity.

D.

Difference In float value of the critical path activities and the float value of the specific activity being analyzed.

Buy Now
Question # 62

The best source of project risk or opportunities is:

Options:

A.

A similar project in another state

B.

Rumors from the local Chamber of Commerce

C.

Failures by other contractors

D.

Internal and external stakeholders

Buy Now
Question # 63

Determine the correct formula and date for the late finish for Activity 2002.

Options:

A.

LS of 2003 less 1 day equaling to 06 Oct 2021

B.

LS of 2003 less 1 day equaling to 06 Nov 2021

C.

LS of 2003 plus 1 day equaling to 07 Oct 2021

D.

LS of 2003 less 1 day equaling to 05 Oct 2021

Buy Now
Exam Code: PSP
Exam Name: Planning & Scheduling Professional (PSP) Exam
Last Update: Nov 2, 2025
Questions: 216
PSP pdf

PSP PDF

$25.5  $84.99
PSP Engine

PSP Testing Engine

$28.5  $94.99
PSP PDF + Engine

PSP PDF + Testing Engine

$40.5  $134.99