Which of the following risks CANNOT be estimated by BILCO with only a resource-loaded schedule?
When should the Project Plan have incorporated the relevant interfaces and requirements of the project contract documents?
Each column must be poured in one day. Each column requires 2,000 cubic feet of concrete. The lift bucket has a capacity of 40 cubic feet. How many lifts will be required per column pour?

What method offers the best chance of the schedule being used effectively to implement the project in the field?
Using the "normal" schedule, and assuming you are billing on the last day of the month for previous month and for appropriate partial months, how many invoices will you have for this project?