Question # 44

What owner action could have mitigated the late completion of the project?

Options:

A.

Hire a more senior project manager.

B.

Self-perform more of the work.

C.

Use a procurement agent to monitor and expedite equipment deliveries.

D.

Prepare better structural steel drawings.

Buy Now
Question # 45

Why does activity 1001 have two successor activities?

Options:

A.

Because the late finish of 1001 and the late start of 7001 require two successors

B.

Because the problem could not effectively work with only one successor

C.

Because there are two defined logic paths for the work

D.

Because the duration of activities 2001, 2002 and 200.f require two successors

Buy Now
Question # 46

Determine the correct formula and date for the late finish for Activity 2002.

Options:

A.

LS.2003 - 1 day -> 11.06.01.

B.

LS.2003 - 1 day -> 10-06-01.

C.

LS.2003 + 1 day -> 10-07-01.

D.

LS.2003 - 1 day -> 10-05-01.

Buy Now
Question # 47

Which of the following risks CANNOT be estimated by BILCO with only a resource-loaded schedule?

Options:

A.

Delay due to SDOT's other projects

B.

Delay due to labor shortage

C.

Liquidated damages on the SDOT contract

D.

Cost overruns due to cement shortage

Buy Now
Question # 48

When should the Project Plan have incorporated the relevant interfaces and requirements of the project contract documents?

Options:

A.

During the Bid Phase

B.

Before the commercial decision to bid on the project

C.

Af1er the award and before the NTP

D.

After the NTP

Buy Now
Question # 49

Each column must be poured in one day. Each column requires 2,000 cubic feet of concrete. The lift bucket has a capacity of 40 cubic feet. How many lifts will be required per column pour?

Options:

A.

80 lifts

B.

50 lifts

C.

5 lifts

D.

20 lifts

Buy Now
Question # 50

What method offers the best chance of the schedule being used effectively to implement the project in the field?

Options:

A.

Issue detailed schedule updates as frequently as possible.

B.

Obtain consent and agreement to the schedule from the key project personnel.

C.

Include detailed and stringent set of scheduling specifications in the contract.

D.

Allow large time contingencies on milestones and completion deadlines.

Buy Now
Question # 51

Schedule Risk may affect the following:

Options:

A.

Activity resource allocation

B.

Long-duration activities

C.

The final milestones phase milestones, critical and non-critical activities

D.

Calendar shifts

Buy Now
Question # 52

Using the "normal" schedule, and assuming you are billing on the last day of the month for previous month and for appropriate partial months, how many invoices will you have for this project?

Options:

A.

42.

B.

36.

C.

40.

D.

37.

Buy Now
Question # 53

What portion of Activity B is on the critical path?

Options:

A.

Last half of the activity

B.

None of it

C.

First half of the activity

D.

The whole activity

Buy Now
Exam Code: PSP
Exam Name: Planning & Scheduling Professional (PSP) Exam
Last Update: Nov 2, 2025
Questions: 216
PSP pdf

PSP PDF

$25.5  $84.99
PSP Engine

PSP Testing Engine

$28.5  $94.99
PSP PDF + Engine

PSP PDF + Testing Engine

$40.5  $134.99