Question 28

Choose two responsibilities of a self-organizing Development Team. (Choose two.)

Options:

A.

Reorder the Product Backlog.

B.

Pull Product Backlog items for the Sprint.

C.

Do the work planned in the Sprint Backlog.

D.

Increase velocity.

E.

Report daily progress to stakeholders.

Question 29

When many Scrum Teams are working on a single product, what best describes the Definition of Done?

(Choose the best answer.)

Options:

A.

Each Scrum Team defines and uses its own. The differences are discussed and reconciled during a

hardening Sprint.

B.

The Scrum Masters from each Scrum Team define a common Definition of Done.

C.

Each Scrum Team uses its own, but must make their definition clear to all other teams so the differences are known.

D.

All Scrum Teams must have a Definition of Done that makes their combined work potentially releasable.

Question 30

Which of the following are true about the Product Owner role? (Choose two.)

Options:

A.

The Product Owner is one person.

B.

The Product Owner is accountable for ordering the Product Backlog.

C.

Multiple people can share the Product Owner role on a Scrum Team.

D.

The Product Owner role can be played by a committee or a team of people.

Question 31

What is the timebox for a Sprint Planning event? (choose the best answer)

Options:

A.

Monthly.

B.

8 hours for a one-month Sprint

C.

Whenever ills done

D.

4 hours for a one-month Sprint

Page: 7 / 18
Exam Code: PSM-I
Exam Name: Professional Scrum Master I
Last Update: May 2, 2024
Questions: 250
PSM-I pdf

PSM-I PDF

$28  $80
PSM-I Engine

PSM-I Testing Engine

$33.25  $95
PSM-I PDF + Engine

PSM-I PDF + Testing Engine

$45.5  $130