Labour Day Special Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: bigdisc65

Legit CTAL-TM_Syll2012 Exam Download

Page: 3 / 8
Question 12

Test Management

You are the Test Manager on a project following an iterative life-cycle model. The project should consist of nine iterations of one month duration each. It is planned to develop the most important features to have a stable core of the application in the first three iterations and to add the additional features in the last six iterations.

At the beginning of the first iteration, only a draft version of the requirements specification document for the core features is available. Assume that during each of the first three iterations, the chosen features are fully completed and unit tested.

Which of the following statements is true in this context?

Number of correct responses: 1

K43 credits

Options:

A.

The system test phase should start when all the requirements are frozen

B.

You should allocate a large effort for system testing during the first three iterations

C.

You should allocate all the effort for the system test phase only in the last iteration

D.

You should apply the same test strategy as used in a sequential life cycle model

Question 13

Test Management

Assume you are currently working on a project developing a system where functional requirements are very well specified. Unfortunately non-functional requirements do almost not exist.

You are the Test Manager. You have to choose a technique for test selection that allows testing of non-functional characteristics, especially reliability.

Which of the following techniques for test selection do you expect being most useful in this scenario?

Number of correct responses: 1

K21 credit

Options:

A.

A model-based technique based on the creation of operational profiles

B.

Ambiguity reviews

C.

Test condition analysis

D.

Cause-effect graphing

Question 14

After the presentation, you are asked to explain the chart.

Assume you have applied a full risk-based testing strategy.

Which of the following answers would you expect to best describe the pie chart?

Number of correct responses: 1

K43 credits

Options:

A.

All the risk items have been covered with tests. No more risk items remain to test

B.

According to the full risk-based testing strategy applied, it is very likely that the highest-risk items, tests and bugs remain in the blue and red areas. Therefore, it is very risky to release the application

C.

Only the lowest-risk items, tests and bugs should remain in the blue and red areas. Therefore the application can be released at any time subject to management of the items identified in those areas

D.

97 percent of the risk items has been tested. No open bugs or test failures remain. Only 3 percent of risk items remains to be covered by the remaining test

Question 15

You can count on well-written requirements, but you can’t count on an adequate contribution of the stakeholders to the quality risk analysis. You have to mitigate the insufficient contribution of the stakeholders because the risk-based testing approach shall minimize the product risks. Your test team has one expert tester in security testing.

Which of the following test activities would you expect to be the less important in this context?

Number of correct responses: 1

K43 credits

Options:

A.

Extract from the defect tracking system of the previous project all the security defects and failures, and classify them to support design and execution of specific tests

B.

Automate all functional and non-functional system tests

C.

Apply systematic and exploratory testing for integration and system test

D.

Perform exploratory testing sessions with adequate charters covering security aspects

Page: 3 / 8
Exam Code: CTAL-TM_Syll2012
Exam Name: ISTQB® Certified Tester Advanced Level - Test Manager [Syllabus 2012]
Last Update: May 2, 2024
Questions: 130
CTAL-TM_Syll2012 pdf

CTAL-TM_Syll2012 PDF

$28  $80
CTAL-TM_Syll2012 Engine

CTAL-TM_Syll2012 Testing Engine

$33.25  $95
CTAL-TM_Syll2012 PDF + Engine

CTAL-TM_Syll2012 PDF + Testing Engine

$45.5  $130